Clean Air Act stationary source · ICIS-AIR NY0000002610500301
KINGS PLAZA ENERGY LLC, Brooklyn, NY: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- No Violation IdentifiedCurrent violation status, as filed
- 41Compliance evaluations since January 1, 2017
- 0High-priority violations since January 1, 2017
- 0Formal enforcement actions since January 1, 2017
KINGS PLAZA ENERGY LLC, at 5100 KINGS PLZ, Brooklyn in Kings County, New York, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “No Violation Identified”. Kings County is on EPA’s Green Book list of areas that do not meet a national air quality standard. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.
What stands out
- The newest of the 47 events on file is a compliance evaluation dated August 12, 2026.
- Its events on file run from April 28, 2017 through August 12, 2026.
- Of its 41 compliance evaluations on file, 5 are a full compliance evaluation.
- The register holds 1,401 air-emissions sources in Kings County, New York.
Every line is computed by formula from the record’s stored figures; nothing is estimated.
Identity
| Facility as filed | KINGS PLAZA ENERGY LLC |
|---|---|
| ICIS-AIR ID | NY0000002610500301 |
| EPA facility registry ID | 110001603480 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (ICIS-AIR high-priority violation field) | No Violation Identified |
| Address | 5100 KINGS PLZ, Brooklyn, NY 11234 |
| County | Kings County |
| In a nonattainment county | Yes (EPA Green Book) |
| Industry (NAICS) | Utilities (NAICS 2211) |
| SIC code | 4931 |
| EPA region | 02 |
Cited to the EPA ICIS-AIR facility file (ECHO download).
Programs and pollutants
Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs KINGS PLAZA ENERGY LLC is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.
Compliance evaluations
- 41Evaluations since January 1, 2017
- 5Full compliance evaluations
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| August 12, 2026 | FCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 23, 2026 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 23, 2026 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| March 23, 2026 | PCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 27, 2025 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 24, 2025 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 24, 2025 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 25, 2024 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 19, 2024 | FCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| May 7, 2024 | PCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 18, 2024 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 18, 2024 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 27, 2023 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 21, 2023 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 21, 2023 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 18, 2022 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 4, 2022 | FCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 21, 2022 | PCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 26, 2022 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 26, 2022 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 26, 2021 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 18, 2021 | PCE Off-Site | U.S. EPA | National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| April 30, 2021 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 30, 2021 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 30, 2020 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 22, 2020 | FCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 16, 2020 | PCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 29, 2020 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 29, 2020 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 25, 2019 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 30, 2019 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 30, 2019 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 30, 2018 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 27, 2018 | FCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 5, 2018 | PCE On-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 1, 2018 | PCE Off-Site | U.S. EPA | Operating Permits |
| April 30, 2018 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 30, 2018 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 27, 2017 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 28, 2017 | PCE Off-Site | State | Stratospheric Ozone Protection; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 28, 2017 | PCE Off-Site | State | Stratospheric Ozone Protection; 40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Review Permit Requirements; Prevention of Accidental Release/General Duty Clause; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
Violations
- 0Violation determinations since January 1, 2017
- 0Of them high-priority
A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.
EPA’s violation history file holds no violation for ICIS-AIR NY0000002610500301 since January 1, 2017.
Enforcement and penalties
0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.
Informal enforcement
EPA’s informal action file holds no notice or warning for ICIS-AIR NY0000002610500301 since January 1, 2017.
Stack tests
- 6Stack tests since January 1, 2017
- 0Recorded as failed
| Date | What EPA recorded | Agency |
|---|---|---|
| September 26, 2025 | Pass | State |
| November 23, 2021 | Pass | U.S. EPA |
| November 23, 2021 | Pass | U.S. EPA |
| November 23, 2021 | Pass | U.S. EPA |
| November 23, 2021 | Pass | U.S. EPA |
| September 20, 2019 | Pass | State |
Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.
Watch this source
One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, NY0000002610500301.
Start the watch
- One source — $99/month
- One county — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110001603480 there.
Nearby on the register
- Air-emissions sources in Kings County
- Every source record in Kings County, A to Z
- Air-emissions sources in New York
- Every source record in New York, A to Z
Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.
What this page shows
This page of the Velarion Records public-records register covers the Clean Air Act compliance record of KINGS PLAZA ENERGY LLC of Brooklyn, NY, under ICIS-AIR NY0000002610500301. The page lists Operating operating status and Major source emissions classification, with No Violation Identified as the current violation status, 41 Compliance evaluations since January 1, 2017, 0 High-priority violations since January 1, 2017, and 0 Formal enforcement actions since January 1, 2017. It also gives EPA facility registry ID 110001603480, the address 5100 KINGS PLZ, Brooklyn, NY 11234, Kings County, and Yes for a nonattainment county.