NPDES ALR10BEFY · Clean Water Act
ROCK SPRINGS LOOP / HILLABEE EXPANSION PROJECT, PHASE 2, Butler, AL: NPDES ALR10BEFY discharge permit, effluent exceedances, inspections, penalties
ROCK SPRINGS LOOP / HILLABEE EXPANSION PROJECT, PHASE 2, Butler, Alabama: General permit coverage ALR10BEFY, held by Transcontinental Gas Pipeline Company, L.L.C.; Construction stormwater; Administratively continued; issued January 7, 2019, term to March 31, 2021, by State; Oil and Gas Pipeline and Related Structures Construction.
Alabama holds 7,857 Construction stormwater coverages of this permit type in EPA’s file; 1,580 were issued before ALR10BEFY. Transcontinental Gas Pipeline Company, L.L.C. holds 2 permits in Alabama.
Other permits held by Transcontinental Gas Pipeline Company, L.L.C.
- MAINLINE D 942.50-942.67, Alexander City: ALR10C576, issued 2024-04-29
Coverages issued nearest ALR10BEFY
- 2018-12-11: FORT PAYNE ELEMENTARY, Fort Payne: ALR10BEFI, held by Fort Payne City Schools
- 2018-12-18: THE HIDEAWAY AT STILLWATERS, Dadeville: ALR10BEHC, held by Lakeview Development Group, LLC
- 2018-12-20: GRAYSON CARTER STORAGE FACILITY, Athens: ALR10BEEK, held by Grayson Carter & Son Contracting, Inc.
- 2018-12-27: CITY OF VALLEY (COMBS PROPERTY) PHASE A, B, C, D, & E, Valley: ALR10BEET, held by City of Valley
- 2019-01-03: AVENUE A TOWN HOMES, Birmingham: ALR10BEER, held by HCP 1st Ave S LLC
- 2019-01-08: CUSTOM CONCRETE WALLS - WAVERLY, Waverly: ALR10BEH8, held by Custom Concrete Walls, Inc.
- 2019-01-11: THE LEDGES OF OAKDALE - SELECTED LOTS, Athens: ALR10BEHR, held by Stone Martin Builders, LLC
- 2019-01-12: GREYSTONE APARTMENTS, Auburn: ALR10BEH6, held by Greystone at Auburn, LLC
- 2019-01-14: CITY OF VALLEY (BURNEY PROPERTY) PHASE A, B, & C, Valley: ALR10BEHA, held by City of Valley
- 2019-01-17: JUDGES SQUARE, Daphne: ALR10BEHP, held by TWO HANDS DESIGN AND DEVELOPMENT LLC
ROCK SPRINGS LOOP / HILLABEE EXPANSION PROJECT, PHASE 2 among its neighbors
10 discharge permits are in the Wahalak Creek subwatershed (HUC 031602010904); ALR10BEFY is one. Its county: 42, 1 major; ALR10BEFY is minor permit.
Other permits in the Wahalak Creek subwatershed (HUC 031602010904)
- ALLEN PIT, Butler: ALG890087, minor, term to 2023-01-31
- ALLEN PIT, Butler: ALR16EH09, minor, term to 2012-04-13
- BUTLER HCR LAGOON, Butler: AL0050211, minor, term to 2026-04-30
- CHOCTAW COUNTY JAIL, Butler: ALR10C6W7, minor, term to 2026-03-31
- CHOCTAW COUNTY REGIONAL LANDFILL, Toxey: ALG160183, minor, term to 2022-01-31
- CHOCTAW COUNTY VFD, Toxey: ALR10C414, minor, term to 2026-03-31
- DIXIE PIPELINE COMPANY LLC, Butler: ALG670174, minor, term to 2017-09-30
- FIRE TOWER ROAD PIT #1, Butler: AL0082287, minor, term to 2024-03-31
- GOC, LTD BUTLER BULK PLANT, Butler: ALG340145, minor, term to 2022-01-31
What stands out
- Its term runs 2 years and 83 days, January 7, 2019 to March 31, 2021; the term ended 2,023 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to October 14, 2026.
- It is one of 13,475 discharge permits on the register in Alabama; 7,857 of them (58%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | ROCK SPRINGS LOOP / HILLABEE EXPANSION PROJECT, PHASE 2 |
|---|---|
| Permittee | Transcontinental Gas Pipeline Company, L.L.C. |
| NPDES ID | ALR10BEFY |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | January 7, 2019 |
| Expires | March 31, 2021 |
| Agency | State |
| Address | Butler, AL 36904 |
| Subwatershed | Wahalak Creek (HUC 031602010904) |
| NAICS | 237120 – Oil and Gas Pipeline and Related Structures Construction |
| SIC | 1623 – Water, Sewer, And Utility Lines |
NPDES ALR10BEFY: effluent limits and exceedances
ROCK SPRINGS LOOP / HILLABEE EXPANSION PROJECT, PHASE 2 (NPDES ALR10BEFY): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ALR10BEFY: no pollutant row on file.
NPDES ALR10BEFY: inspections, violations and enforcement
NPDES ALR10BEFY (ROCK SPRINGS LOOP / HILLABEE EXPANSION PROJECT, PHASE 2): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES ALR10BEFY
NPDES ALR10BEFY: one email when its EPA record changes — $99/month.
Permits near NPDES ALR10BEFY
NPDES ALR10BEFY: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.