NPDES GAR248235 · Clean Water Act
MILNER PRIM AND UPRATE (EPD-WCD), Milner, GA: NPDES GAR248235 discharge permit, effluent exceedances, inspections, penalties
MILNER PRIM AND UPRATE (EPD-WCD), Milner, Georgia: General permit coverage GAR248235, held by AGL Resources; Construction stormwater; Effective; issued September 23, 2013, term to July 31, 2018.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 24 were issued before GAR248235.
Coverages issued nearest GAR248235
- 2013-09-23: GLYNN COUNTY SCHOOL SIDEWALKS - US 341 (GLYNN COUNTY): GAR248228, held by GLYNN COUNTY BOARD OF COMMISSIONERS
- 2013-09-23: COMMERCE NORTH SOUTH CONNECTING SIDEWALKS, Commerce: GAR248229, held by CITY OF COMMERCE
- 2013-09-23: BROOKMONT D (COTTAGES) LOT -51, N/A: GAR248230, held by Kerley Family Homes
- 2013-09-23: MASSEY AIRPORT ROAD 115/25 KV SUBSTATION: GAR248231, held by GEORGIA TRANSMISSION CORP
- 2013-09-23: STREET AND DRAINAGE IMPROVEMENTS FOR DEWBERRY ROAD 2017 LMIG (COFFEE COUNTY): GAR248234, held by COFFEE COUNTY BOARD OF COMMISSIONERS
- 2013-09-23: MILLER'S FERRY LOOP WATER EXTENSION HWY 41 SEGMENT, Calhoun: GAR248236, held by City of Calhoun Utilities
- 2013-09-23: STREET AND DRAINAGE IMPROVEMENTS FOR MELROSE AND LONG CREEK ROADS: GAR248238, held by ECHOLS COUNTY BOARD OF COMMISSIONERS
- 2013-09-23: VALENTINE PARK LIFT STATION AND FORCEMAIN, Jefferson: GAR248241, held by JACKSON COUNTY WATER & SEWERAGE AUTHORITY
- 2013-09-23: TALLANT FARMS OUTFALL SEWER, Cumming: GAR248243, held by DR Horton, Inc.
- 2013-09-23: FT. BENNING DISTRIBUTION SYS. REINFORCEMENTS (EPD-WCD), Fort Benning: GAR248244, held by US Army - DPW: Mr. Craig Taylor
MILNER PRIM AND UPRATE (EPD-WCD) among its neighbors
7 discharge permits are in the Big Towaliga River subwatershed (HUC 030701031201); GAR248235 is one.
Other permits in the Big Towaliga River subwatershed (HUC 030701031201)
- 1818 ABBEY ROAD LOT 60, Griffin: GAR396CCA, minor, term to 2028-07-31
- 5 STAR FORD-LINCOLN, Warner Robins: GAR147260, minor, term to 2018-07-31
- HAMPTON INN, Johns Creek: GAR152139, minor, term to 2018-07-31
- PATRICK ACQUISITIONS OFFICE WAREHOUSES, Milner: GAR18BE6F, minor, term to 2028-07-31
- SPRING CHASE APARTMENTS - PHASE II, Barnesville: GAR18B8F3, minor, term to 2028-07-31
- VINTAGE PARK LOTS B-5, B-6, C-10, C-17, Milner: GAR395F57, minor, term to 2025-01-31
Identity
| Facility | MILNER PRIM AND UPRATE (EPD-WCD) |
|---|---|
| Permittee | AGL Resources |
| NPDES ID | GAR248235 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 23, 2013 |
| Expires | July 31, 2018 |
| Address | Milner, GA 30257 |
| Subwatershed | Big Towaliga River (HUC 030701031201) |
NPDES GAR248235: effluent limits and exceedances
MILNER PRIM AND UPRATE (EPD-WCD) (NPDES GAR248235): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR248235: no pollutant row on file.
NPDES GAR248235: inspections, violations and enforcement
NPDES GAR248235 (MILNER PRIM AND UPRATE (EPD-WCD)): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR248235
NPDES GAR248235: one email when its EPA record changes — $99/month.
Permits near NPDES GAR248235
NPDES GAR248235: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.