HIGHLAND POINTE AT OAKMONT LOT 143, held by Taylor Morrison of Georgia, LLC, holds NPDES permit GAR362830. EPA’s file records it issued September 23, 2013 and expiring July 31, 2018. The status and dates are as EPA’s permit file stood when Velarion loaded it (October 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What the register holds for HIGHLAND POINTE AT OAKMONT LOT 143: its NPDES ID, its permit type and status, its dates, its address in Dawsonville, Georgia. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES GAR362830.
Identity
| Facility as filed | HIGHLAND POINTE AT OAKMONT LOT 143 |
|---|---|
| Permittee as filed | Taylor Morrison of Georgia, LLC |
| NPDES ID | GAR362830 |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | September 23, 2013 |
| Expiration date | July 31, 2018 |
| Address | Dawsonville, GA 30534 |
| Subwatershed | Black Mill Creek-Etowah River (HUC 031501040107) |
| NAICS | 236115 – New Single-Family Housing Construction [except For-Sale Builders] |
| SIC | 1521 – Single-Family Housing Construction |
Cited to the EPA ICIS-NPDES permit file (ECHO download) and EPA’s NAICS/SIC and component files, the same download.
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES GAR362830.
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES GAR362830.
Inspections
EPA’s inspection file holds no inspection for NPDES GAR362830.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES GAR362830.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, GAR362830.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID GAR362830 there.
HIGHLAND POINTE AT OAKMONT LOT 143, Dawsonville, Georgia: Coverage under a general permit GAR362830, held by Taylor Morrison of Georgia, LLC; Construction stormwater; Effective; issued September 23, 2013, term to July 31, 2018; New Single-Family Housing Construction [except For-Sale Builders].
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 24 were issued before GAR362830. Taylor Morrison of Georgia, LLC holds 532 permits in Georgia.
Other permits held by Taylor Morrison of Georgia, LLC
- 311 WILLS ROAD - ENCLAVE AT WILLS PARK, Alpharetta: GAR147453, issued 2013-09-23
- PERIMETER PARK, Chamblee: GAR149993, issued 2013-09-23
- GARNER PRESERVE SEWER TRUNK LINE, Lilburn: GAR254510, issued 2023-08-01
- THE PRESERVE AT FOWLER MILL - AKA FOWLER MILL SUBDIVISION PHASE 3: GAR348824, issued 2013-09-23
- BROOKSTONE - PHASE 2A - AKA OAKBROOK; AKA PILGRIM MILL; AKA PILGRIM MILL ROAD TR: GAR354436, issued 2013-09-23
- RIVERBROOKE POD J: GAR354442, issued 2013-09-23
- BROOKSTONE - PHASE 2A- AKA OAKBROOK; AKA PILGRIM MILL; AKA PILGRIM MILL ROAD TRA: GAR355010, issued 2013-09-23
- BROOKSTONE PHASE 2A - AKA OAKBROOK; AKA PILGRIM MILL; AKA PILGRIM MILL ROAD TRAC: GAR355012, issued 2013-09-23
- BROOKSTONE PHASE 2A - AKA OAKBROOK; AKA PILGRIM MILL; AKA PILGRIM MILL ROAD TRAC: GAR355015, issued 2013-09-23
- BROOKSTONE PHASE 2A - AKA OAKBROOK; AKA PILGRIM MILL; AKA PILGRIM MILL ROAD TRAC: GAR355016, issued 2013-09-23
Coverages issued nearest GAR362830
- 2013-09-23: HERITAGE PLANTATION ON THE ETOWAH PHASE 1 LOT 20, Ball Ground: GAR362822, held by Riverrock Ventures, LLC
- 2013-09-23: LAUREL CANYON LOT 25, Canton: GAR362823, held by Meritage Homes of Georgia
- 2013-09-23: HIGHLAND POINTE AT OAKMONT LOT 142, Dawsonville: GAR362826, held by Taylor Morrison of Georgia, LLC
- 2013-09-23: LAUREL CANYON LOT 142, Canton: GAR362827, held by Meritage Homes of Georgia
- 2013-09-23: HIGHLAND POINTE AT OAKMONT LOT 151, Dawsonville: GAR362828, held by Taylor Morrison of Georgia, LLC
- 2013-09-23: THE COVE AT 1300 LOT 367, Blairsville: GAR362831, held by Martin Milton
- 2013-09-23: WENTWORTH MANOR, LOT 20: GAR362832, held by Drey Investment Group
- 2013-09-23: IVEY SPRINGS PHASE IV LOT 278 (PAULDING), Dallas: GAR362835, held by George Thomas Homes
- 2013-09-23: STONEY CREEK ESTATES LOT 111: GAR362844, held by DR Horton- Crown LLC
- 2013-09-23: COTTAGES AT STILLWOOD LOT -14, Newnan: GAR362845, held by Kerley Family Homes
HIGHLAND POINTE AT OAKMONT LOT 143 among its neighbors
108 discharge permits are in the Black Mill Creek-Etowah River subwatershed (HUC 031501040107); GAR362830 is one.
Other permits in the Black Mill Creek-Etowah River subwatershed (HUC 031501040107)
- 124 STORAGE WAY, Dawsonville: GAR18AD13, minor, term to 2028-07-31
- APPLICABLE SECTION OF HUBBARD TOWN 115 KV TRANSMISSION LINE, Unknown: GAR248317, minor, term to 2018-07-31
- B.K. RESIDENTIAL, LLC, Dawson: GAR346719, minor, term to 2018-07-31
- BLACK MILL CREEK, Dawsonville: GAR372951, minor, term to 2018-07-31
- BLACKS MILL ELEMENTARY SCHOOL ADDITIONS AND RENOVATIONS, Dawsonville: GAR18BD20, minor, term to 2028-07-31
- BTD MANUFACTURING, INC. WAREHOUSE, Dawsonville: GAIS14977, minor, term to 2027-05-31
- CARLISLE ROAD REALIGNMENT AND PAVING, Dawsonville: GAR247044, minor, term to 2018-07-31
- DAWSON MARKETPLACE, Unknown: GAR149899, minor, term to 2018-07-31
- DAWSON POINTE LOT 58, Dawsonville: GAR346696, minor, term to 2018-07-31
- ETOWAH WATER & SEWER AUTHORITY (DAWSON FOREST WRF), Dawsonville: GAJ020232, minor, term to 2017-12-27
Nearby on the register
- Discharge permits in Dawsonville
- Every permit record in Dawsonville, A to Z
- Discharge permits in Georgia
- Every permit record in Georgia, A to Z
Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.
What this page shows
Of the 291 storm water construction permits in Dawsonville, 0.0% have a violation on file, and HIGHLAND POINTE AT OAKMONT LOT 143 belongs to that group. Measured by issue date, 0.0% of Dawsonville's 291 permits came before HIGHLAND POINTE AT OAKMONT LOT 143. The Black Mill Creek-Etowah River subwatershed, HUC 031501040107, contains 108 NPDES permits, including this permit.