NPDES IN0061361 · Clean Water Act
DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION, New Castle, IN: NPDES IN0061361 discharge permit, effluent exceedances, inspections, penalties
DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION, New Castle, Indiana: Individual permit IN0061361; Administratively continued; issued December 1, 2017, term to February 28, 2023, by IDEM; discharges to PIERCE DITCH, VIA LARIMORE DRAIN.
- Dilution factor: 1 limit, 4 violations of any kind, 3 effluent exceedances, latest February 28, 2025, largest 950% over the limit.
- Chlorine, total residual: 2 limits, 5 violations of any kind, 1 effluent exceedance, latest February 28, 2025, largest 0% over the limit.
- Streamflow: 4 limits, 14 violations of any kind.
- pH: 2 limits, 4 violations of any kind.
- Solids, total suspended: 2 limits, 4 violations of any kind.
- Fluoride, total [as F]: 2 limits, 4 violations of any kind.
- Iron, total recoverable: 2 limits, 4 violations of any kind.
- Zinc, total recoverable: 2 limits, 4 violations of any kind.
- Chromium, total recoverable: 2 limits, 4 violations of any kind.
- Flow, in conduit or thru treatment plant: 2 limits, 4 violations of any kind.
- Solids, total dissolved: 2 limits, 4 violations of any kind.
- Oil and grease, hexane extr method: 2 limits, 2 violations of any kind.
- Temperature, water deg. fahrenheit: 1 limit, 2 violations of any kind.
- Flow, total: 1 limit, 2 violations of any kind.
- Oil & Grease: 0 limits, 2 violations of any kind.
- Nitrogen, ammonia total [as N]: 0 limits, 2 violations of any kind.
- March 31, 2026: Evaluation (S).
DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION among its neighbors
23 discharge permits are in the Elliott Run-Big Blue River subwatershed (HUC 051202040103); IN0061361 is one. Its county: 32, 2 major; IN0061361 is minor permit.
Other permits in the Elliott Run-Big Blue River subwatershed (HUC 051202040103)
- AITCHISON SUBDIVISION, New Carlisle: INRA15932, minor, term to 2030-05-06
- ALLEGHENY LUDLUM, LLC, New Castle: IN0045284, major, term to 2012-06-30
- ASHBURY FIELDS SUBDIVISION, New Castle: INRA16434, minor, term to 2030-07-15
- BOARS HEAD NEW CASTLE SOUTH EXPANSION, New Castle: INRA10534, minor, term to 2027-09-18
- BOARS HEAD PROVISIONS CO INC, New Castle: INRM02647, minor, term to 2025-04-23
- BOARS HEAD PROVISIONS COMPANY INCORPORATED NEW CASTLE NORTH, New Castle: INRM02699, minor, term to 2025-08-23
- BROOKFIELD FARMS, New Castle: INRA16723, minor, term to 2030-08-27
- GOCO DUNKIN' NEW CASTLE, New Castle: INRA11999, minor, term to 2028-06-19
- HENRY COUNTY SHELL BUILDING, New Castle: INRA06906, minor, term to 2026-01-31
- HOOSIER AUTO, New Castle: INRA10383, minor, term to 2027-10-13
What stands out
- Its term runs 5 years and 89 days, December 1, 2017 to February 28, 2023; the term ended 1,324 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on March 31, 2026, 197 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- 2 of its 16 pollutants on file have an effluent exceedance (13%); 14 are under a numeric limit; the largest exceedance is Dilution factor at 950% over its limit.
- It is one of 13,164 discharge permits on the register in Indiana; the file names no program for it, and it is a minor discharger.
Identity
| Facility | DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION |
|---|---|
| Permittee | DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION |
| NPDES ID | IN0061361 |
| Status | Administratively continued |
| Type | Individual permit |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | December 1, 2017 |
| Expires | February 28, 2023 |
| Agency | IDEM |
| Address | New Castle, IN 47362 |
| Receiving water | PIERCE DITCH, VIA LARIMORE DRAIN |
| Subwatershed | Elliott Run-Big Blue River (HUC 051202040103) |
| SIC | 4911 – Electric Services |
| Other EPA IDs (FRS) | RCRA handler INR000024562; ICIS-AIR source IN0000001806500032 |
NPDES IN0061361: effluent limits and exceedances
DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION (NPDES IN0061361): 16 pollutants on file, 14 limited; 16 with a violation of any kind, 2 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Dilution factor | 1 | 4 | 3 | February 28, 2025 | 950% over the limit |
| Chlorine, total residual | 2 | 5 | 1 | February 28, 2025 | 0% over the limit |
| Streamflow | 4 | 14 | 0 | ||
| pH | 2 | 4 | 0 | ||
| Solids, total suspended | 2 | 4 | 0 | ||
| Fluoride, total [as F] | 2 | 4 | 0 | ||
| Iron, total recoverable | 2 | 4 | 0 | ||
| Zinc, total recoverable | 2 | 4 | 0 | ||
| Chromium, total recoverable | 2 | 4 | 0 | ||
| Flow, in conduit or thru treatment plant | 2 | 4 | 0 | ||
| Solids, total dissolved | 2 | 4 | 0 | ||
| Oil and grease, hexane extr method | 2 | 2 | 0 | ||
| Temperature, water deg. fahrenheit | 1 | 2 | 0 | ||
| Flow, total | 1 | 2 | 0 | ||
| Oil & Grease | 0 | 2 | 0 | ||
| Nitrogen, ammonia total [as N] | 0 | 2 | 0 |
NPDES IN0061361: inspections, violations and enforcement
NPDES IN0061361: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| March 31, 2026 | Evaluation | S |
NPDES IN0061361 (DUKE ENERGY INDIANA, LLC - HENRY CO. GENERATING STATION): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES IN0061361
NPDES IN0061361: one email when its EPA record changes — $99/month.
Permits near NPDES IN0061361
NPDES IN0061361: 16 pollutant rows, 1 dated events; ICIS-NPDES download, loaded October 14, 2026.