FALL ROCK-MANCHESTER 69 KV TRANSMISSION LINE REBUILD PROJECT, Big Creek, KY: NPDES KYR10T043 discharge permit, effluent exceedances, inspections, penalties

FALL ROCK-MANCHESTER 69 KV TRANSMISSION LINE REBUILD PROJECT, Big Creek, Kentucky: General permit coverage KYR10T043, held by Fall Rock-Manchester 69 kV Transmission Line Rebuild Project; Construction stormwater; Effective; issued January 8, 2025, term to December 31, 2029, by KY DEP; discharges to Island Creek.

Kentucky holds 1,852 Construction stormwater coverages of this permit type in EPA’s file; 80 were issued before KYR10T043.

Coverages issued nearest KYR10T043

FALL ROCK-MANCHESTER 69 KV TRANSMISSION LINE REBUILD PROJECT among its neighbors

3 discharge permits are in the Hector Branch-Red Bird River subwatershed (HUC 051002030207); KYR10T043 is one. Its county: 32, 1 major; KYR10T043 is minor permit.

Other permits in the Hector Branch-Red Bird River subwatershed (HUC 051002030207)

What stands out

  • Its term runs 4 years and 357 days, January 8, 2025 to December 31, 2029.
  • No dated event in the 365 days to September 15, 2026.
  • It is one of 5,741 discharge permits on the register in Kentucky; 1,852 of them (32%) are in its program, Construction stormwater, and it is a minor discharger.

Identity

FacilityFALL ROCK-MANCHESTER 69 KV TRANSMISSION LINE REBUILD PROJECT
PermitteeFall Rock-Manchester 69 kV Transmission Line Rebuild Project
NPDES IDKYR10T043
StatusEffective
TypeGeneral permit coverage
ClassMinor
Facility typeNon-POTW
ProgramConstruction stormwater
IssuedJanuary 8, 2025
ExpiresDecember 31, 2029
AgencyKY DEP
AddressBig Creek, KY 40914
Receiving waterIsland Creek
SubwatershedHector Branch-Red Bird River (HUC 051002030207)

NPDES KYR10T043: effluent limits and exceedances

FALL ROCK-MANCHESTER 69 KV TRANSMISSION LINE REBUILD PROJECT (NPDES KYR10T043): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.

NPDES KYR10T043: no pollutant row on file.

NPDES KYR10T043: inspections, violations and enforcement

NPDES KYR10T043 (FALL ROCK-MANCHESTER 69 KV TRANSMISSION LINE REBUILD PROJECT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.

Watch NPDES KYR10T043

NPDES KYR10T043: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES KYR10T043

NPDES KYR10T043: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.