NPDES TXR1507RQ · Clean Water Act
BRAZOS COUNTY BRIDGE SCOUR REPAIR PROJECT CIP 24-614, Bryan, TX: NPDES TXR1507RQ discharge permit, effluent exceedances, inspections, penalties
BRAZOS COUNTY BRIDGE SCOUR REPAIR PROJECT CIP 24-614, Bryan, Texas: General permit coverage TXR1507RQ, held by SOLID BRIDGE CONSTRUCTION, LLC; Construction stormwater; Effective; issued July 30, 2024, term to March 4, 2028; discharges to WICKSON CREEK.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 8,400 were issued before TXR1507RQ. SOLID BRIDGE CONSTRUCTION, LLC holds 23 permits in Texas.
Other permits held by SOLID BRIDGE CONSTRUCTION, LLC
- FOSTERS RIDGE CHANNEL REHAB PHASE 1, Conroe: TXR1516ON, issued 2023-09-28
- SMITHVILLE SOUTHEAST DRAINATE IMPROVEMENTS, Smithville: TXR1517YC, issued 2026-04-29
- LAKE TRISTAN DAM, Woodville: TXR1518YC, issued 2026-04-29
- INTERCONTINENTAL CENTER DR OFFSITE WATERLINE & DETENTION 2, Houston: TXR1528PH, issued 2023-12-14
- WAVERLY PLACE SECTION 3, New Waverly: TXR1531SL, issued 2024-10-15
- HOMESTEAD HILL DRAINAGE AND PAVING, New Waverly: TXR1533QC, issued 2024-03-01
- GT BARS, Montgomery: TXR1545UD, issued 2025-04-02
- G105-04-01 CHANNEL REHABILITATION, Deer Park: TXR1546ZB, issued 2026-08-06
- GLO CDBG-MIT DRAINAGE IMPROVEMENTS, Somerville: TXR1547TB, issued 2024-12-19
- TRIO LAKES WATER TRANSFER STATION, Cypress: TXR1547WD, issued 2025-10-16
Coverages issued nearest TXR1507RQ
- 2024-07-29: CONCRETE BATCH PLANT CHURCHILL PHASE 3A, Van Alstyne: TXR1572RP, held by Tiseo Paving Co.
- 2024-07-29: CONCRETE BATCH PLANT SUPPORTING VENETIAN AT WESTON PH2, Weston: TXR1573RP, held by Tiseo Paving Co.
- 2024-07-30: CREEKVIEW MEADOWS, Pilot Point: TXR1503RQ, held by Bloomfield Homes, L.P.
- 2024-07-30: CYPRESS GREEN MASON BASIN, Hockley: TXR1504RQ, held by Northtex Construction, LLC
- 2024-07-30: LAS PALAPAS TALLEY RD, San Antonio: TXR1505RQ, held by Field Construction, Inc.
- 2024-07-30: LEGACY POINT, Cypress: TXR1510RQ, held by Carter Construction, LLC
- 2024-07-30: LINDE NEDERLAND OCIOSBL PIPELINE PROJECT, Beaumont: TXR1511RQ, held by Linde Inc.
- 2024-07-30: 146TH ST RECONSTRUCTION FROM QUAKER TO INDIANA, Lubbock: TXR1513RQ, held by Lone Star Dirt & Paving, Ltd.
- 2024-07-30: 560 ROBERTS RUN, Sherman: TXR1514RQ, held by Valencia Romero Investments LLC
- 2024-07-30: YORKTOWN BOULEVARD RODD FIELD TO OSO CREEK BRIDGE, Corpus Christi: TXR1515RQ, held by J E Construction Services, LLC
BRAZOS COUNTY BRIDGE SCOUR REPAIR PROJECT CIP 24-614 among its neighbors
9 discharge permits are in the Upper Wickson Creek subwatershed (HUC 120701030602); TXR1507RQ is one. Its county: 458, 8 major; TXR1507RQ is minor permit.
Other permits in the Upper Wickson Creek subwatershed (HUC 120701030602)
- BRYAN ASU, Bryan: TXR1582YT, minor, term to 2028-03-04
- COULTER BUSINESS PARK, Bryan: TXR1547NX, minor, term to 2028-03-04
- COULTER FIELD, Bryan: TXR05DS44, minor, term to 2026-08-13
- GOOSENECK TRAILER MFG, Bryan: TXR05GZ76, minor, term to 2026-08-13
- RSI BRYAN FRAC YARD, Bryan: TXR05FF36, minor, term to 2026-08-13
- STELLA RANCH PHASE 1, Bryan: TXR1588WQ, minor, term to 2028-03-04
- WHISPERING WILLOWS, Bryan: TXR1550WU, minor, term to 2028-03-04
- WICKSON CREEK SUD KENT B WATSON PLANT, Bryan: TXR1543UD, minor, term to 2028-03-04
What stands out
- Its term runs 3 years and 218 days, July 30, 2024 to March 4, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 39,714 discharge permits on the register in Texas; 23,986 of them (60%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | BRAZOS COUNTY BRIDGE SCOUR REPAIR PROJECT CIP 24-614 |
|---|---|
| Permittee | SOLID BRIDGE CONSTRUCTION, LLC |
| NPDES ID | TXR1507RQ |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 30, 2024 |
| Expires | March 4, 2028 |
| Address | Bryan, TX 77808 |
| Receiving water | WICKSON CREEK |
| Subwatershed | Upper Wickson Creek (HUC 120701030602) |
NPDES TXR1507RQ: effluent limits and exceedances
BRAZOS COUNTY BRIDGE SCOUR REPAIR PROJECT CIP 24-614 (NPDES TXR1507RQ): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES TXR1507RQ: no pollutant row on file.
NPDES TXR1507RQ: inspections, violations and enforcement
NPDES TXR1507RQ (BRAZOS COUNTY BRIDGE SCOUR REPAIR PROJECT CIP 24-614): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES TXR1507RQ
NPDES TXR1507RQ: one email when its EPA record changes — $99/month.
Permits near NPDES TXR1507RQ
NPDES TXR1507RQ: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.