Clean Air Act stationary source · ICIS-AIR IN0000001808900121

US STEEL CORPORATION GARY WORKS, Gary, IN: Clean Air Act compliance record, inspections, violations, penalties

US STEEL CORPORATION GARY WORKS, at 1 N BROADWAY, Gary in Lake County, Indiana, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “Unaddressed-State”. Lake County is on EPA’s Green Book list of areas that do not meet a national air quality standard. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.

Identity

Facility as filedUS STEEL CORPORATION GARY WORKS
ICIS-AIR IDIN0000001808900121
EPA facility registry ID110000398374
Operating statusOperating
Emissions classificationMajor source
Current violation status (ICIS-AIR high-priority violation field)Unaddressed-State
Address1 N BROADWAY, Gary, IN 46402-3101
CountyLake County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Primary metal manufacturing (NAICS 3311)
SIC code3312
EPA region05

Cited to the EPA ICIS-AIR facility file (ECHO download).

Programs and pollutants

Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs US STEEL CORPORATION GARY WORKS is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.

Compliance evaluations

The newest 50 of 109.

DateWhat EPA recordedAgencyPrograms
August 20, 2026PCE On-SiteStateTitle V Permits
August 19, 2026PCE Off-SiteU.S. EPAState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
July 21, 2026PCE On-SiteStateTitle V Permits
July 21, 2026PCE On-SiteStateTitle V Permits
July 15, 2026PCE Off-SiteU.S. EPANational Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
June 25, 2026PCE Off-SiteU.S. EPAInformation Requests, Monitoring, & Recordkeeping; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 30, 2026PCE On-SiteStateTitle V Permits
February 18, 2026PCE On-SiteStateTitle V Permits
January 21, 2026PCE On-SiteStateTitle V Permits
January 6, 2026PCE On-SiteStateTitle V Permits
November 19, 2025PCE On-SiteStateTitle V Permits
November 12, 2025PCE On-SiteStateTitle V Permits
October 1, 2025PCE On-SiteStateTitle V Permits
July 24, 2025FCE On-SiteStateTitle V Permits
July 24, 2025PCE On-SiteStateTitle V Permits
April 1, 2025PCE On-SiteStateTitle V Permits
February 5, 2025PCE On-SiteStateTitle V Permits
January 8, 2025PCE On-SiteStateTitle V Permits
November 19, 2024PCE On-SiteStateTitle V Permits
October 31, 2024PCE On-SiteStateTitle V Permits
October 16, 2024PCE On-SiteStateTitle V Permits
October 1, 2024PCE On-SiteStateTitle V Permits
August 6, 2024PCE On-SiteStateTitle V Permits
June 25, 2024PCE Off-SiteU.S. EPAInformation Requests, Monitoring, & Recordkeeping; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
June 25, 2024PCE On-SiteStateTitle V Permits
May 30, 2024PCE Off-SiteU.S. EPAState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 29, 2024PCE Off-SiteU.S. EPAState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 16, 2024PCE Off-SiteU.S. EPAState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 15, 2024PCE Off-SiteU.S. EPAMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 23, 2024PCE On-SiteStateTitle V Permits
April 8, 2024PCE Off-SiteU.S. EPAMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 26, 2024PCE On-SiteStateTitle V Permits
January 17, 2024PCE On-SiteStateTitle V Permits
December 19, 2023PCE On-SiteStateTitle V Permits
November 15, 2023PCE On-SiteStateTitle V Permits
August 8, 2023PCE On-SiteStateTitle V Permits
August 8, 2023PCE On-SiteStateTitle V Permits
June 27, 2023PCE On-SiteStateTitle V Permits
June 13, 2023PCE On-SiteStateTitle V Permits
February 1, 2023PCE On-SiteStateTitle V Permits
December 6, 2022PCE On-SiteStateTitle V Permits
November 15, 2022PCE On-SiteStateTitle V Permits
November 1, 2022PCE On-SiteStateTitle V Permits
October 4, 2022PCE On-SiteStateTitle V Permits
July 26, 2022FCE On-SiteStateTitle V Permits
June 28, 2022PCE On-SiteStateTitle V Permits
June 23, 2022PCE On-SiteStateTitle V Permits
March 16, 2022PCE On-SiteStateTitle V Permits
February 1, 2022PCE On-SiteStateTitle V Permits
January 6, 2022PCE On-SiteStateTitle V Permits

Violations

A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.

DateWhat EPA recordedAgencyPrograms
November 25, 2025HPV day-zero determinationStateMACT Standards (40 CFR Part 63)
August 27, 2025Earliest FRV determinationStateMACT Standards (40 CFR Part 63)
October 28, 2024Earliest FRV determinationStateTitle V Permits
October 28, 2024HPV day-zero determinationStateTitle V Permits
July 30, 2024Earliest FRV determinationStateTitle V Permits
April 26, 2024Earliest FRV determinationStateTitle V Permits
January 29, 2024Earliest FRV determinationStateTitle V Permits
October 30, 2023HPV day-zero determinationStateTitle V Permits
October 30, 2023Earliest FRV determinationStateTitle V Permits
July 23, 2023Earliest FRV determinationStateTitle V Permits
April 27, 2023Earliest FRV determinationStateTitle V Permits
February 14, 2023HPV day-zero determinationStateTitle V Permits
January 21, 2023Earliest FRV determinationStateTitle V Permits
November 16, 2022Earliest FRV determinationStateTitle V Permits
October 28, 2022Earliest FRV determinationStateTitle V Permits
October 24, 2022HPV day-zero determinationStateTitle V Permits
July 29, 2022Earliest FRV determinationStateTitle V Permits
May 23, 2022Earliest FRV determinationStateTitle V Permits
January 21, 2022Earliest FRV determinationStateTitle V Permits
October 29, 2021Earliest FRV determinationStateTitle V Permits
October 18, 2021HPV day-zero determinationStateTitle V Permits
July 21, 2021Earliest FRV determinationStateTitle V Permits
May 25, 2021Earliest FRV determinationStateTitle V Permits
April 30, 2021Earliest FRV determinationStateTitle V Permits
November 6, 2020Earliest FRV determinationStateTitle V Permits
April 29, 2020HPV day-zero determinationStateTitle V Permits
March 6, 2020Earliest FRV determinationStateTitle V Permits
January 30, 2020Earliest FRV determinationStateTitle V Permits
January 28, 2020HPV day-zero determinationStateTitle V Permits
November 5, 2019HPV day-zero determinationStateTitle V Permits
October 28, 2019Earliest FRV determinationStateTitle V Permits
August 7, 2019Earliest FRV determinationStateTitle V Permits
April 28, 2019HPV day-zero determinationStateMACT Standards (40 CFR Part 63); Title V Permits
March 9, 2019Earliest FRV determinationStateMACT Standards (40 CFR Part 63); Title V Permits
October 25, 2018HPV day-zero determinationStateTitle V Permits
September 12, 2018Earliest FRV determinationStateTitle V Permits
August 2, 2018HPV day-zero determinationStateTitle V Permits
June 19, 2018Earliest FRV determinationStateTitle V Permits
April 24, 2018HPV day-zero determinationStateTitle V Permits
April 24, 2018HPV day-zero determinationStateMACT Standards (40 CFR Part 63)
March 23, 2018Earliest FRV determinationStateTitle V Permits
February 28, 2018HPV day-zero determinationStateTitle V Permits
January 10, 2018HPV day-zero determinationStateTitle V Permits
November 2, 2017HPV day-zero determinationStateTitle V Permits
October 4, 2017Earliest FRV determinationStateTitle V Permits
August 29, 2017HPV day-zero determinationStateTitle V Permits

Enforcement and penalties

9 formal enforcement actions since January 1, 2017, 9 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.

DateWhat EPA recordedAgencyPenalty, as filed
May 15, 2026Administrative OrderState$49,750
February 5, 2025Administrative OrderState$64,250
June 13, 2024Administrative OrderState$83,250
May 11, 2023Administrative OrderState$29,250
August 19, 2021Administrative OrderState$37,400
April 20, 2021Administrative OrderState$74,250
April 20, 2021Administrative OrderState$14,000
August 9, 2019Administrative OrderState$66,123
March 30, 2017Civil Judicial ActionU.S. EPA$2,200,000

Informal enforcement

DateWhat EPA recordedAgency
August 16, 2024Notice of ViolationU.S. EPA
November 25, 2019Notice of ViolationState

Stack tests

The newest 50 of 192.

DateWhat EPA recordedAgency
June 24, 2026PassState
June 24, 2026PassState
June 24, 2026PassState
June 23, 2026PassState
June 23, 2026PassState
June 23, 2026PassState
June 16, 2026PassState
June 16, 2026PassState
June 16, 2026PassState
June 16, 2026PassState
June 11, 2026PassState
June 11, 2026PassState
June 11, 2026PassState
June 11, 2026PassState
March 25, 2026PassState
March 25, 2026PassState
March 25, 2026PassState
March 24, 2026PassState
January 27, 2026PassState
January 27, 2026PassState
December 4, 2025PassState
July 15, 2025FailState
October 22, 2024PassState
October 22, 2024PassState
August 8, 2024PassState
August 2, 2024PassState
August 2, 2024PassState
July 31, 2024PassState
July 31, 2024PassState
July 31, 2024FailState
July 31, 2024PassState
April 9, 2024PassState
April 9, 2024PassState
February 7, 2024PassState
February 7, 2024PassState
February 7, 2024PassState
February 7, 2024PassState
February 7, 2024PassState
February 7, 2024PassState
January 31, 2024PassState
January 31, 2024PassState
January 10, 2024PassState
January 10, 2024PassState
January 10, 2024PassState
December 7, 2023PassState
December 7, 2023PassState
December 7, 2023PassState
December 5, 2023PassState
December 5, 2023PassState
December 5, 2023PassState

Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.

Watch this source

One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, IN0000001808900121.

Start the watch

How often?
  • One source — $99/month
  • One county — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110000398374 there.

Nearby on the register

Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.

What this page shows

This page of the Velarion Records public-records register covers the Clean Air Act compliance record for US STEEL CORPORATION GARY WORKS in Gary, IN, at ICIS-AIR ID IN0000001808900121. It lists 109 compliance evaluations, 18 high-priority violations, and 9 formal enforcement actions since January 1, 2017. The facility's operating status is Operating, its emissions classification is Major source, and its current violation status is Unaddressed-State.