Clean Air Act stationary source · ICIS-AIR MS0000002812900085
LEAF RIVER ENERGY CENTER LLC, LEAF RIVER ENERGY CENTER, Taylorsville, MS: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- No Violation IdentifiedCurrent violation status, as filed
- 6Compliance evaluations since January 1, 2017
- 0High-priority violations since January 1, 2017
- 0Formal enforcement actions since January 1, 2017
LEAF RIVER ENERGY CENTER LLC, LEAF RIVER ENERGY CENTER, at 855 SMITH COUNTY ROAD 5, Taylorsville in Smith County, Mississippi, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “No Violation Identified”. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.
Identity
| Facility as filed | LEAF RIVER ENERGY CENTER LLC, LEAF RIVER ENERGY CENTER |
|---|---|
| ICIS-AIR ID | MS0000002812900085 |
| EPA facility registry ID | 110039139580 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (ICIS-AIR high-priority violation field) | No Violation Identified |
| Address | 855 SMITH COUNTY ROAD 5, Taylorsville, MS 39481 |
| County | Smith County |
| In a nonattainment county | No (EPA Green Book) |
| Industry (NAICS) | Pipeline transportation (NAICS 4862) |
| EPA region | 04 |
Cited to the EPA ICIS-AIR facility file (ECHO download).
Programs and pollutants
Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs LEAF RIVER ENERGY CENTER LLC, LEAF RIVER ENERGY CENTER is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.
Compliance evaluations
- 6Evaluations since January 1, 2017
- 5Full compliance evaluations
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| August 20, 2026 | FCE On-Site | State | MACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| September 24, 2024 | FCE On-Site | State | MACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 19, 2022 | FCE On-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| March 11, 2022 | PCE On-Site | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| July 15, 2020 | FCE On-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 11, 2017 | FCE On-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
Violations
- 2Violation determinations since January 1, 2017
- 0Of them high-priority
A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| April 18, 2022 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| February 21, 2017 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
Enforcement and penalties
0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| April 18, 2022 | Notice of Violation | State |
| February 21, 2017 | Notice of Violation | State |
Stack tests
- 102Stack tests since January 1, 2017
- 0Recorded as failed
The newest 50 of 102.
| Date | What EPA recorded | Agency |
|---|---|---|
| January 15, 2026 | Pass | State |
| January 15, 2026 | Pass | State |
| January 15, 2026 | Pass | State |
| January 15, 2026 | Pass | State |
| January 14, 2026 | Pass | State |
| January 14, 2026 | Pass | State |
| January 14, 2026 | Pass | State |
| January 14, 2026 | Pass | State |
| January 13, 2026 | Pass | State |
| January 13, 2026 | Pass | State |
| January 13, 2026 | Pass | State |
| January 13, 2026 | Pass | State |
| April 3, 2025 | Pass | State |
| April 2, 2025 | Pass | State |
| April 2, 2025 | Pass | State |
| April 2, 2025 | Pass | State |
| April 2, 2025 | Pass | State |
| April 2, 2025 | Pass | State |
| January 29, 2025 | Pass | State |
| January 29, 2025 | Pass | State |
| January 29, 2025 | Pass | State |
| January 29, 2025 | Pass | State |
| January 28, 2025 | Pass | State |
| January 28, 2025 | Pass | State |
| January 28, 2025 | Pass | State |
| January 28, 2025 | Pass | State |
| May 2, 2024 | Pass | State |
| May 1, 2024 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| May 16, 2023 | Pass | State |
| May 16, 2023 | Pass | State |
| May 16, 2023 | Pass | State |
| May 16, 2023 | Pass | State |
| June 3, 2022 | Pass | State |
| June 3, 2022 | Pass | State |
| June 3, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
| June 2, 2022 | Pass | State |
Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.
Watch this source
One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, MS0000002812900085.
Start the watch
- One source — $99/month
- One county — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110039139580 there.
Nearby on the register
- Air-emissions sources in Smith County
- Every source record in Smith County, A to Z
- Air-emissions sources in Mississippi
- Every source record in Mississippi, A to Z
Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.