Clean Air Act stationary source · ICIS-AIR WI0000005503500002
WRR ENVIRONMENTAL SERVICES CO INC, Eau Claire, WI: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- Unaddressed-StateCurrent violation status, as filed
- 32Compliance evaluations since January 1, 2017
- 4High-priority violations since January 1, 2017
- 0Formal enforcement actions since January 1, 2017
WRR ENVIRONMENTAL SERVICES CO INC, at 5200 RYDER RD, Eau Claire in Eau Claire County, Wisconsin, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “Unaddressed-State”. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.
Identity
| Facility as filed | WRR ENVIRONMENTAL SERVICES CO INC |
|---|---|
| ICIS-AIR ID | WI0000005503500002 |
| EPA facility registry ID | 110070725846 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (ICIS-AIR high-priority violation field) | Unaddressed-State |
| Address | 5200 RYDER RD, Eau Claire, WI 547015140 |
| County | Eau Claire County |
| In a nonattainment county | No (EPA Green Book) |
| Industry (NAICS) | Chemical manufacturing (NAICS 3259) |
| SIC code | 7389 |
| EPA region | 05 |
Cited to the EPA ICIS-AIR facility file (ECHO download).
Programs and pollutants
Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs WRR ENVIRONMENTAL SERVICES CO INC is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.
Compliance evaluations
- 32Evaluations since January 1, 2017
- 3Full compliance evaluations
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| August 17, 2026 | PCE Off-Site | State | Title V Permits |
| August 17, 2026 | PCE Off-Site | State | Title V Permits |
| August 17, 2026 | PCE Off-Site | State | Title V Permits |
| August 17, 2026 | PCE Off-Site | State | Title V Permits |
| April 1, 2026 | PCE Off-Site | State | Title V Permits |
| February 27, 2026 | PCE Off-Site | State | Title V Permits |
| January 30, 2026 | PCE Off-Site | State | Title V Permits |
| January 2, 2026 | PCE Off-Site | State | Title V Permits |
| November 26, 2025 | PCE Off-Site | State | Title V Permits |
| November 3, 2025 | PCE Off-Site | State | Title V Permits |
| October 7, 2025 | PCE Off-Site | State | Title V Permits |
| July 7, 2025 | PCE Off-Site | State | Title V Permits |
| June 4, 2025 | PCE Off-Site | State | Title V Permits |
| May 6, 2025 | PCE Off-Site | State | Title V Permits |
| April 7, 2025 | PCE Off-Site | State | Title V Permits |
| March 6, 2025 | PCE Off-Site | State | Title V Permits |
| February 4, 2025 | PCE Off-Site | State | Title V Permits |
| February 4, 2025 | PCE Off-Site | State | Title V Permits |
| January 6, 2025 | PCE Off-Site | State | Title V Permits |
| December 11, 2024 | PCE Off-Site | State | Title V Permits |
| November 6, 2024 | PCE Off-Site | State | Title V Permits |
| October 8, 2024 | PCE Off-Site | State | Title V Permits |
| October 8, 2024 | PCE Off-Site | State | Title V Permits |
| April 9, 2024 | PCE Off-Site | State | MACT Standards (40 CFR Part 63); Title V Permits |
| May 2, 2023 | PCE On-Site | U.S. EPA | MACT Standards (40 CFR Part 63) |
| December 31, 2021 | PCE Off-Site | U.S. EPA | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| September 28, 2021 | FCE On-Site | State | Title V Permits |
| September 11, 2019 | FCE On-Site | State | Title V Permits |
| February 20, 2019 | PCE Off-Site | State | MACT Standards (40 CFR Part 63); National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 14, 2018 | PCE Off-Site | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| October 24, 2018 | PCE On-Site | U.S. EPA | Hazardous Air Pollutants; MACT Standards (40 CFR Part 63); New Source Performance Standards; New Source Review Permit Requirements; Operating Permits; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| September 15, 2017 | FCE On-Site | State | Title V Permits |
Violations
- 14Violation determinations since January 1, 2017
- 4Of them high-priority
A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| March 11, 2024 | Earliest FRV determination | State | Title V Permits |
| March 5, 2024 | Earliest FRV determination | State | Title V Permits |
| March 1, 2024 | Earliest FRV determination | State | Title V Permits |
| January 11, 2024 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63) |
| January 11, 2024 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63) |
| January 11, 2024 | Earliest FRV determination | State | Title V Permits |
| January 11, 2024 | Earliest FRV determination | State | Title V Permits |
| September 28, 2021 | HPV day-zero determination | State | MACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| June 9, 2020 | HPV day-zero determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| September 11, 2019 | HPV day-zero determination | State | MACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| February 20, 2019 | Earliest FRV determination | State | National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61) |
| December 20, 2018 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| September 7, 2017 | HPV day-zero determination | State | MACT Standards (40 CFR Part 63); New Source Performance Standards; Title V Permits |
| August 14, 2017 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); New Source Performance Standards; Title V Permits |
Enforcement and penalties
0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| April 9, 2024 | Notice of Violation | State |
| November 15, 2021 | Notice of Violation | State |
| June 10, 2020 | Notice of Violation | State |
| October 24, 2019 | Notice of Violation | State |
| October 24, 2019 | Notice of Violation | State |
| March 29, 2019 | Notice of Violation | U.S. EPA |
| February 20, 2019 | Notice of Violation | State |
| January 14, 2019 | Notice of Violation | State |
| January 5, 2018 | Notice of Violation | State |
Stack tests
- 2Stack tests since January 1, 2017
- 0Recorded as failed
| Date | What EPA recorded | Agency |
|---|---|---|
| June 4, 2024 | Pass | State |
| March 28, 2019 | Pass | State |
Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.
Watch this source
One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, WI0000005503500002.
Start the watch
- One source — $99/month
- One county — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110070725846 there.
Nearby on the register
- Air-emissions sources in Eau Claire County
- Every source record in Eau Claire County, A to Z
- Air-emissions sources in Wisconsin
- Every source record in Wisconsin, A to Z
Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.