Clean Air Act stationary source · ICIS-AIR WI0000005503900025
GRAYMONT WESTERN LIME - EDEN, Eden, WI: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- No Violation IdentifiedCurrent violation status, as filed
- 14Compliance evaluations since January 1, 2017
- 0High-priority violations since January 1, 2017
- 0Formal enforcement actions since January 1, 2017
GRAYMONT WESTERN LIME - EDEN, at N4520 COUNTY ROAD V, Eden in Fond du Lac County, Wisconsin, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “No Violation Identified”. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.
Identity
| Facility as filed | GRAYMONT WESTERN LIME - EDEN |
|---|---|
| ICIS-AIR ID | WI0000005503900025 |
| EPA facility registry ID | 110000593910 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (ICIS-AIR high-priority violation field) | No Violation Identified |
| Address | N4520 COUNTY ROAD V, Eden, WI 53019 |
| County | Fond du Lac County |
| In a nonattainment county | No (EPA Green Book) |
| Industry (NAICS) | Nonmetallic mineral product manufacturing (NAICS 3274) |
| EPA region | 05 |
Cited to the EPA ICIS-AIR facility file (ECHO download).
Programs and pollutants
Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs GRAYMONT WESTERN LIME - EDEN is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.
Compliance evaluations
- 14Evaluations since January 1, 2017
- 4Full compliance evaluations
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| August 6, 2026 | PCE Off-Site | State | Title V Permits |
| April 30, 2026 | PCE Off-Site | State | Title V Permits |
| October 27, 2025 | PCE Off-Site | State | Title V Permits |
| May 21, 2025 | PCE Off-Site | State | Title V Permits |
| January 17, 2025 | PCE Off-Site | State | Title V Permits |
| January 17, 2025 | PCE Off-Site | State | Title V Permits |
| January 15, 2025 | PCE Off-Site | State | Title V Permits |
| October 18, 2024 | PCE Off-Site | State | Title V Permits |
| October 18, 2024 | PCE Off-Site | State | Title V Permits |
| May 30, 2024 | FCE On-Site | State | Title V Permits |
| October 19, 2022 | PCE On-Site | U.S. EPA | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| July 14, 2022 | FCE On-Site | State | Title V Permits |
| September 17, 2020 | FCE On-Site | State | Title V Permits |
| June 6, 2018 | FCE On-Site | State | Title V Permits |
Violations
- 3Violation determinations since January 1, 2017
- 0Of them high-priority
A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| April 11, 2024 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| April 11, 2024 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| April 11, 2024 | Earliest FRV determination | State | New Source Performance Standards |
Enforcement and penalties
0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| July 1, 2024 | Warning Letter | State |
Stack tests
- 17Stack tests since January 1, 2017
- 0Recorded as failed
| Date | What EPA recorded | Agency |
|---|---|---|
| March 3, 2026 | Pass | State |
| September 23, 2025 | Pass | State |
| March 6, 2025 | Pass | State |
| August 14, 2024 | Pass | State |
| March 5, 2024 | Pass | State |
| December 12, 2023 | Pass | State |
| March 14, 2023 | Pass | State |
| March 16, 2022 | Pass | State |
| December 16, 2021 | Pass | State |
| September 21, 2021 | Pass | State |
| March 9, 2021 | Pass | State |
| February 4, 2020 | Pass | State |
| December 19, 2019 | Pass | State |
| October 8, 2019 | Pass | State |
| August 27, 2019 | Pass | State |
| August 7, 2018 | Pass | State |
| September 19, 2017 | Pass | State |
Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.
Watch this source
One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, WI0000005503900025.
Start the watch
- One source — $99/month
- One county — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110000593910 there.
Nearby on the register
- Air-emissions sources in Fond du Lac County
- Every source record in Fond du Lac County, A to Z
- Air-emissions sources in Wisconsin
- Every source record in Wisconsin, A to Z
Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.