Clean Air Act stationary source · ICIS-AIR WI0000005507300034
WI PUBLIC SERVICE WESTON POWER PLANT, Kronenwetter, WI: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- No Violation IdentifiedCurrent violation status, as filed
- 32Compliance evaluations since January 1, 2017
- 0High-priority violations since January 1, 2017
- 0Formal enforcement actions since January 1, 2017
WI PUBLIC SERVICE WESTON POWER PLANT, at 2491 OLD HWY 51, Kronenwetter in Marathon County, Wisconsin, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “No Violation Identified”. Marathon County is on EPA’s Green Book list of areas that do not meet a national air quality standard. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.
Identity
| Facility as filed | WI PUBLIC SERVICE WESTON POWER PLANT |
|---|---|
| ICIS-AIR ID | WI0000005507300034 |
| EPA facility registry ID | 110043779783 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (ICIS-AIR high-priority violation field) | No Violation Identified |
| Address | 2491 OLD HWY 51, Kronenwetter, WI 54455 |
| County | Marathon County |
| In a nonattainment county | Yes (EPA Green Book) |
| Industry (NAICS) | Utilities (NAICS 2211) |
| SIC code | 4911 |
| EPA region | 05 |
Cited to the EPA ICIS-AIR facility file (ECHO download).
Programs and pollutants
Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs WI PUBLIC SERVICE WESTON POWER PLANT is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.
Compliance evaluations
- 32Evaluations since January 1, 2017
- 5Full compliance evaluations
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| August 3, 2026 | PCE Off-Site | State | Title V Permits |
| August 3, 2026 | PCE Off-Site | State | Title V Permits |
| March 13, 2026 | FCE On-Site | State | Title V Permits |
| February 24, 2026 | PCE Off-Site | State | Title V Permits |
| February 23, 2026 | PCE Off-Site | State | Title V Permits |
| February 6, 2026 | PCE Off-Site | State | Title V Permits |
| January 23, 2026 | PCE Off-Site | State | Title V Permits |
| October 28, 2025 | PCE Off-Site | State | Title V Permits |
| April 23, 2025 | PCE Off-Site | State | Title V Permits |
| February 28, 2025 | PCE Off-Site | State | Title V Permits |
| February 27, 2025 | PCE Off-Site | State | Title V Permits |
| February 17, 2025 | PCE Off-Site | State | Title V Permits |
| January 28, 2025 | PCE Off-Site | State | Title V Permits |
| January 28, 2025 | PCE Off-Site | State | Title V Permits |
| January 21, 2025 | PCE Off-Site | State | Title V Permits |
| December 26, 2024 | PCE Off-Site | State | New Source Review Permit Requirements |
| December 16, 2024 | PCE Off-Site | State | Title V Permits |
| October 21, 2024 | PCE Off-Site | State | Title V Permits |
| July 29, 2024 | PCE Off-Site | State | Prevention of Significant Deterioration of Air Quality |
| January 30, 2024 | FCE On-Site | State | Title V Permits |
| December 21, 2023 | PCE Off-Site | State | Prevention of Significant Deterioration of Air Quality |
| May 26, 2023 | PCE Off-Site | State | Title V Permits |
| January 11, 2023 | PCE Off-Site | State | New Source Review Permit Requirements; Prevention of Significant Deterioration of Air Quality; Title V Permits |
| January 1, 2023 | PCE Off-Site | State | Title V Permits |
| April 21, 2022 | FCE On-Site | State | Title V Permits |
| April 1, 2022 | PCE Off-Site | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| February 8, 2022 | PCE Off-Site | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| May 1, 2021 | PCE Off-Site | State | New Source Review Permit Requirements; Prevention of Significant Deterioration of Air Quality |
| June 19, 2020 | FCE On-Site | State | Title V Permits |
| February 7, 2020 | PCE Off-Site | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 23, 2018 | PCE Off-Site | State | New Source Review Permit Requirements; Prevention of Significant Deterioration of Air Quality |
| March 14, 2018 | FCE On-Site | State | Title V Permits |
Violations
- 17Violation determinations since January 1, 2017
- 0Of them high-priority
A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| December 27, 2024 | Earliest FRV determination | State | New Source Review Permit Requirements |
| July 29, 2024 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
| January 17, 2024 | Earliest FRV determination | State | Title V Permits |
| January 17, 2024 | Earliest FRV determination | State | Title V Permits |
| December 21, 2023 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
| December 21, 2023 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
| May 26, 2023 | Earliest FRV determination | State | Title V Permits |
| January 4, 2023 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| April 21, 2022 | Earliest FRV determination | State | Title V Permits |
| February 14, 2022 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
| February 14, 2022 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
| May 3, 2021 | Earliest FRV determination | State | New Source Review Permit Requirements |
| December 23, 2020 | Earliest FRV determination | State | Title V Permits |
| April 7, 2020 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| November 14, 2019 | Earliest FRV determination | State | New Source Review Permit Requirements; Title V Permits |
| November 14, 2019 | Earliest FRV determination | State | New Source Review Permit Requirements |
| July 23, 2018 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
Enforcement and penalties
0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| January 7, 2025 | Warning Letter | State |
| August 23, 2024 | Warning Letter | State |
| February 5, 2024 | Warning Letter | State |
| June 2, 2023 | Warning Letter | State |
| February 1, 2023 | Notice of Violation | State |
| May 2, 2022 | Warning Letter | State |
| February 21, 2022 | Warning Letter | State |
| May 7, 2021 | Warning Letter | State |
| January 11, 2021 | Warning Letter | State |
| August 21, 2020 | Notice of Violation | State |
| February 7, 2020 | Warning Letter | State |
| July 25, 2018 | Warning Letter | State |
| July 25, 2018 | Warning Letter | State |
Stack tests
- 75Stack tests since January 1, 2017
- 0Recorded as failed
The newest 50 of 75.
| Date | What EPA recorded | Agency |
|---|---|---|
| June 30, 2026 | Pass | State |
| June 29, 2026 | Pass | State |
| June 24, 2026 | Pass | State |
| June 23, 2026 | Pass | State |
| June 23, 2026 | Pass | State |
| June 22, 2026 | Pass | State |
| October 20, 2025 | Pass | State |
| October 20, 2025 | Pass | State |
| July 14, 2025 | Pass | State |
| July 14, 2025 | Pass | State |
| July 14, 2025 | Pass | State |
| July 14, 2025 | Pass | State |
| May 12, 2025 | Pass | State |
| May 12, 2025 | Pass | State |
| May 12, 2025 | Pass | State |
| May 12, 2025 | Pass | State |
| May 12, 2025 | Pass | State |
| November 5, 2024 | Pass | State |
| October 22, 2024 | Pass | State |
| July 22, 2024 | Pass | State |
| July 15, 2024 | Pass | State |
| July 15, 2024 | Pass | State |
| July 15, 2024 | Pass | State |
| July 15, 2024 | Pass | State |
| May 14, 2024 | Pass | State |
| May 13, 2024 | Pass | State |
| May 13, 2024 | Pass | State |
| May 13, 2024 | Pass | State |
| December 11, 2023 | Pass | State |
| October 23, 2023 | Pass | State |
| September 19, 2023 | Pass | State |
| July 10, 2023 | Pass | State |
| July 10, 2023 | Pass | State |
| July 10, 2023 | Pass | State |
| July 10, 2023 | Pass | State |
| July 10, 2023 | Pass | State |
| May 22, 2023 | Pass | State |
| May 22, 2023 | Pass | State |
| May 22, 2023 | Pass | State |
| May 22, 2023 | Pass | State |
| May 22, 2023 | Pass | State |
| October 11, 2022 | Pass | State |
| August 10, 2022 | Pass | State |
| August 9, 2022 | Pass | State |
| August 9, 2022 | Pass | State |
| July 12, 2022 | Pass | State |
| May 16, 2022 | Pass | State |
| May 16, 2022 | Pass | State |
| May 16, 2022 | Pass | State |
| October 12, 2021 | Pass | State |
Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.
Watch this source
One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, WI0000005507300034.
Start the watch
- One source — $99/month
- One county — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110043779783 there.
Nearby on the register
- Air-emissions sources in Marathon County
- Every source record in Marathon County, A to Z
- Air-emissions sources in Wisconsin
- Every source record in Wisconsin, A to Z
Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.