EPA Air · stack tests by county and year
Air-emissions stack tests in Clayton County, Georgia, 2026
- 12Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Clayton County, Georgia during 2026. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Clayton County facility page.
Clayton County, Georgia, 2026
- Inspections 35
Air-emissions stack tests in Clayton County, other years
What stands out
- Stack tests in Clayton County, Georgia, fell from 20 in 2025, the previous year on file, to 12 in 2026.
- The county’s file for stack tests holds 10 years of events, from 2017 through 2026.
- Its 12 stack tests rank 22nd of the 46 county cells in Georgia for 2026.
- Its 12 stack tests are 1.7% of the 704 the state’s file holds for 2026.
Every line is computed by formula from the state’s stored file; nothing is estimated.
Air-emissions stack tests recorded in Clayton County, Georgia, 2026
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2026-07-17 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-17 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-15 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-15 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-13 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-13 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-13 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-07-13 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-06-03 | DELTA AIR LINES INC. - TECHNICAL OPERATIONS CENTER | Pass | State |
| 2026-04-22 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-04-22 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
| 2026-04-21 | ATLANTA GAS LIGHT COMPANY - RIVERDALE LNG PLANT — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.
What this page shows
This page covers Clean Air Act facilities in the EPA air register with stack tests in Clayton county, GA, for 2026. It lists 4 stack tests recorded in 2026.