EPA Air · stack tests by county and year
Air-emissions stack tests in Shelby County, Indiana, 2018
- 59Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Shelby County, Indiana during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Shelby County facility page.
Shelby County, Indiana, 2018
Air-emissions stack tests in Shelby County, other years
What stands out
- Stack tests in Shelby County, Indiana, rose from 18 in 2017, the previous year on file, to 59 in 2018.
- The county’s file for stack tests holds 10 years of events, from 2017 through 2026.
- Its 59 stack tests rank 6th of the 60 county cells in Indiana for 2018.
- Its 59 stack tests are 3.7% of the 1,605 the state’s file holds for 2018.
Every line is computed by formula from the state’s stored file; nothing is estimated.
Air-emissions stack tests recorded in Shelby County, Indiana, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-12-18 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2018-12-18 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2018-12-11 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-12-11 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-12-11 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-12-11 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-12-11 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-12-11 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-06 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-06 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-06 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-06 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-06 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-11-06 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-10-24 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2018-10-13 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-09-19 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2018-09-19 | ANR PIPELINE COMPANY SHELBYVILLE COMPRESSOR STATION | Pass | State |
| 2018-08-29 | CHARTER MANUFACTURING COMPANY INCORPORATED | Pass | State |
| 2018-08-29 | CHARTER MANUFACTURING COMPANY INCORPORATED | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-09 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-05-08 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-04-03 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-04-03 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-04-03 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-04-03 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-04-03 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
| 2018-04-03 | KNAUF INSULATION INCORPORATED — high-priority violation on file | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.
What this page shows
This page covers Clean Air Act facilities in the EPA air register with stack tests in Shelby county, IN, in 2018. Stack tests recorded in 2018: 59.