Velarion Records

Clean Water Act discharge permit · NPDES FLR05C545

H.L. CULBREATH BAYSIDE POWER STATION, Tampa, FL: NPDES FLR05C545 discharge permit, effluent exceedances, inspections, penalties

H.L. CULBREATH BAYSIDE POWER STATION, held by Tampa Electric Co, holds NPDES permit FLR05C545, which discharges to Hillsborough Bay. EPA’s file records it issued February 15, 2021 and expiring February 14, 2026. The status and dates are as EPA’s permit file stood when Velarion loaded it (October 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

Identity

Facility as filedH.L. CULBREATH BAYSIDE POWER STATION
Permittee as filedTampa Electric Co
NPDES IDFLR05C545
Permit statusAdministratively continued (past its expiration date and still in force until reissued)
Permit typeCoverage under a general permit
Discharger classMinor discharger
Facility typeNot a publicly owned treatment works
ProgramIndustrial stormwater
IssuedFebruary 15, 2021
Expiration dateFebruary 14, 2026
Issuing agencyFlorida Department of Environmental Protection
AddressTampa, FL 33619
Receiving waterHILLSBOROUGH BAY
SubwatershedDelaney Creek-Archie Creek Frontal (HUC 031002060302)
NAICS221112 – Fossil Fuel Electric Power Generation
SIC4911 – Electric Services
Other EPA IDs (FRS)RCRA handler FLD000654582

Cited to the EPA ICIS-NPDES permit file (ECHO download) and EPA’s NAICS/SIC and component files, the same download; cross-program IDs from EPA’s FRS facility-registry crosswalk.

Effluent limits and exceedances

An effluent exceedance is a discharge monitoring report value over the permit’s numeric limit (EPA’s violation code E90). A violation of any kind also counts a report not filed. Each row is EPA’s own count for that pollutant.

Pollutant or measureLimitsViolations, any kindEffluent exceedancesLatest exceedanceLargest exceedance, as filed
Iron, total recoverable200

EPA’s effluent violation file records no exceedance of a numeric limit for NPDES FLR05C545.

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

DateWhat EPA recordedAgency
June 10, 2026WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMPST6
June 10, 2026WW Storm Water Non-Construction - Failure to Maintain RecordsST6

Velarion’s copy of EPA’s ICIS-NPDES files does not include the inspections, formal enforcement actions and informal enforcement actions files, so this page shows none of them. EPA’s free Detailed Facility Report on ECHO lists this permit’s inspections, enforcement actions and penalties.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, FLR05C545.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID FLR05C545 there.

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.

The Pay Desk is the free weekly executive pay briefing — one company at a time, every number traceable to a public filing.
We’ll email you a link to confirm. Unsubscribe any time.