Clean Water Act discharge permit · NPDES FLR20IY13
MITCHELL BUSINESS PARK PHASE 1, Trinity, FL: NPDES FLR20IY13 discharge permit, effluent exceedances, inspections, penalties
- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 1Inspections on file
- 0Formal enforcement actions
MITCHELL BUSINESS PARK PHASE 1, held by Arco Murray Construction Company, holds NPDES permit FLR20IY13. EPA’s file records it issued January 30, 2026 and expiring January 29, 2031.
MITCHELL BUSINESS PARK PHASE 1, Trinity, Florida: Coverage under a general permit FLR20IY13, held by Arco Murray Construction Company; Construction stormwater; Effective; issued January 30, 2026, term to January 29, 2031, by Florida Department of Environmental Protection.
- March 25, 2026: Notice of Noncompliance Issued (State).
- March 11, 2026: WW Storm Water Construction - Failure to Implement SWPPP/SWMP (ST6).
- March 11, 2026: WW Storm Water Construction - Failure to properly operate and maintain BMPs (ST6).
- March 11, 2026: Evaluation (S).
Florida holds 15,654 Construction stormwater coverages of this permit type in EPA’s file; 12,790 were issued before FLR20IY13. Arco Murray Construction Company holds 11 permits in Florida.
Other permits held by Arco Murray Construction Company
- CMNY TRANSITIONS, Pinellas Park: FLR20GH63, issued May 18, 2023
- PRINCETON OAKS 2B, Orlando: FLR20GO46, issued August 26, 2023
- PLANT CITY INDUSTRIAL FACILITY, Plant City: FLR20HD40, issued April 11, 2024
- GATES CREEK CORPORATE CENTER, Bradenton: FLR20HE02, issued April 19, 2024
- SONOCO PLANT CITY EXPANSION, Plant City: FLR20HK59, issued July 22, 2024
- LAKE MARY I-4 COMMERCE CENTER, Lake Mary: FLR20IV54, issued December 20, 2025
- LIGHTARD KNOTT SPEC DEVELOPMENT, Fort Myers: FLR20JB21, issued March 8, 2026
- FOUNDRY EPOC AKA EDGEWOOD PARK OF COMMERCE, Orlando: FLR20JC57, issued March 27, 2026
- LAKEVIEW INDUSTRIAL, Tampa: FLR20JF78, issued May 7, 2026
- PUBLIC STORAGE CASSELBERRY, Casselberry: FLR20JI53, issued June 13, 2026
Coverages issued nearest FLR20IY13
- January 30, 2026: FOUNDATION INDUSTRIAL COMPLEX, Palm Bay, FLR20IY07, held by Foundation Industrial Park LLC
- January 30, 2026: SITE 35 WETLANDS MITIGATION, Orlando, FLR20IY08, held by HEALTHEON, INC.
- January 30, 2026: LEE HEALTH 5C, Cape Coral, FLR20IY10, held by Bravo Site Works
- January 30, 2026: TALIS TRAILS 1, Tallahassee, FLR20IY11, held by Jax Utilities Management, Inc.
- January 30, 2026: ADVENT HEALTH ORLANDO MEDICAL OFFICE BUILDING, Orlando, FLR20IY12, held by Batson-Cook Construction
- January 30, 2026: AMELIA ISLAND SUBSTATION, Fernandina Beach, FLR20IY14, held by Florida Public Utilities Co.
- January 30, 2026: DEF FO GINNIE-HAILLE-ARCHER TRANSMISSION LINE, High Springs, FLR20IY15, held by Duke Energy Florida LLC
- January 30, 2026: THE STATION AT HAMLIN, Winter Garden, FLR20IY16, held by Hughes Brothers Construction, Inc.
- January 30, 2026: THE STATION AT HAMLIN EXPORT SITE, Winter Garden, FLR20IY17, held by Hughes Brothers Construction, Inc.
- January 30, 2026: STATE AVE TOWNHOMES, Panama City, FLR20IY18, held by C-Miles Construction
Other permits in Trinity
- DOBINSON WAREHOUSE, Trinity: FLR10XO45, minor permit, permit term to April 5, 2030
- EXALT HEALTH TRINITY, Trinity: FLR10XR45, minor permit, permit term to May 22, 2030
- EXALT REHAB HOSPITAL, Trinity: FLR20IS66, minor permit, permit term to November 5, 2030
- GLOBAL PHOTONICS, Trinity: FLRNEG012, minor permit, permit term to September 18, 2029
- MITCHELL BLVD FROM CHURCHILL PKWY TO TRINITY OAKS, Trinity: FLR10XZ17, minor permit, permit term to September 27, 2030
- NORTH HUNTING CREEK, Trinity: FLR10XW16, minor permit, permit term to July 30, 2030
- TRINITY SPORTS, Trinity: FLR20HP60, minor permit, permit term to October 6, 2029
- VLOC INC -TRINITY OPERATIONS, Trinity: FLRNEF198, minor permit, permit term to November 20, 2018
Identity
| Facility as filed | MITCHELL BUSINESS PARK PHASE 1 |
|---|---|
| Permittee as filed | Arco Murray Construction Company |
| NPDES ID | FLR20IY13 |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | January 30, 2026 |
| Expiration date | January 29, 2031 |
| Issuing agency | Florida Department of Environmental Protection |
| Address | Trinity, FL 34655 |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES FLR20IY13.
Inspections, violations and enforcement
- 2Single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| March 11, 2026 | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | ST6 |
| March 11, 2026 | WW Storm Water Construction - Failure to properly operate and maintain BMPs | ST6 |
Inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| March 11, 2026 | Evaluation | S |
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| March 25, 2026 | Notice of Noncompliance Issued | State |
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, FLR20IY13.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Trinity
- Every permit record in Trinity, A to Z
- Discharge permits in Florida
- Every permit record in Florida, A to Z
Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.