SLATER MILL PHASE 2 - LOT - 173, held by Jefferson Homes, Inc, holds NPDES permit GAR367622. EPA’s file records it issued September 23, 2013 and expiring July 31, 2018.
SLATER MILL PHASE 2 - LOT - 173, Na, Georgia: Coverage under a general permit GAR367622, held by Jefferson Homes, Inc; Construction stormwater; Effective; issued September 23, 2013, term to July 31, 2018; New Single-Family Housing Construction [except For-Sale Builders].
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 24 were issued before GAR367622. Jefferson Homes, Inc holds 105 permits in Georgia.
Other permits held by Jefferson Homes, Inc
- THE VINEYARDS AT BUTNER: GAR338348, issued September 23, 2013
- STONEY CREEK ESTATES PHASE III - LOT 125: GAR362348, issued September 23, 2013
- STONEY CREEK ESTATES PHASE III - LOT 238: GAR362357, issued September 23, 2013
- STONEY CREEK ESTATES PHASE II - LOT 246: GAR362369, issued September 23, 2013
- SLATER MILL PHASE 2 -LOT - 39, Na: GAR367584, issued September 23, 2013
- SLATER MILL PHASE 2 LOT -40, Na: GAR367585, issued September 23, 2013
- SLATER MILL PHASE 2 LOT 41, Na: GAR367586, issued September 23, 2013
- SLATER MILL PHASE 2 LOT 43, Na: GAR367599, issued September 23, 2013
- SLATER MILL PHASE 2 LOT 106, Na: GAR367610, issued September 23, 2013
- SLATER MILL PHASE 2 LOT -107, Na: GAR367612, issued September 23, 2013
Coverages issued nearest GAR367622
- September 23, 2013: SLATER MILL PHASE 2 LOT -117, Na, GAR367613, held by Jefferson Homes, Inc
- September 23, 2013: SLATER MILL PHASE 2 LOT -118, Na, GAR367614, held by Jefferson Homes, Inc
- September 23, 2013: SLATER MILL PHASE 2 LOT - 137, Na, GAR367615, held by Jefferson Homes, Inc
- September 23, 2013: AZALEA LAKES LOT 33, GAR367619, held by Pinnacle Homes
- September 23, 2013: SLATER MILL PHASE 2 LOT 138, Na, GAR367620, held by Jefferson Homes, Inc
- September 23, 2013: SLATER MILL PHASE 2 LOT- 181, Na, GAR367623, held by Jefferson Homes, Inc
- September 23, 2013: SLATER MILL PHASE 2 LOT - 182, Na, GAR367624, held by Jefferson Homes , Inc
- September 23, 2013: THE WATERFORD LOT 476, GAR367625, held by Smith Built Contracting, LLC
- September 23, 2013: SLATER MIL PHASE 2 LOT - 183, Na, GAR367626, held by Jefferson Homes, Inc
- September 23, 2013: SLATER MILL PHASE 3- LOT 48, Na, GAR367629, held by Jefferson Homes, Inc
SLATER MILL PHASE 2 - LOT - 173 among its neighbors
EPA’s permit file holds 265 discharge permits in the No Business Creek-Yellow River subwatershed (HUC 030701030401), GAR367622 among them.
Other permits in the No Business Creek-Yellow River subwatershed (HUC 030701030401)
- 2589 CENTERVILLE HWY, Snellville: GAR18AD7D, minor permit, permit term to July 31, 2028
- ALDI INC. STORE #32 EXPANSION, Snellville: GAR153F58, minor permit, permit term to July 31, 2023
- ATL EAST DATA CENTER, Conyers: GAR18B011, minor permit, permit term to January 31, 2025
- ATL2D PUF, Conyers: GAR18BC8B, minor permit, permit term to July 31, 2028
- BETHANY PARK, Snellville: GAR18B943, minor permit, permit term to July 31, 2028
- BOJANGLES, Temple: GAR151577, minor permit, permit term to July 31, 2018
- BRISCOE PARK RECREATION CENTER, Snellville: GAR18B838, minor permit, permit term to July 31, 2028
- BROOKWOOD GREEN, Snellville: GAR396E55, minor permit, permit term to July 31, 2028
- CAMP WESTMINSTER, Conyers: GAR147241, minor permit, permit term to July 31, 2018
- CAMP WESTMINSTER WAKEBOARD LAKE, Conyers: GAR153011, minor permit, permit term to July 31, 2018
What the register holds for SLATER MILL PHASE 2 - LOT - 173: its NPDES ID, its permit type and status, its dates, its address in Na, Georgia. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES GAR367622.
Identity
| Facility as filed | SLATER MILL PHASE 2 - LOT - 173 |
|---|---|
| Permittee as filed | Jefferson Homes, Inc |
| NPDES ID | GAR367622 |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | September 23, 2013 |
| Expiration date | July 31, 2018 |
| Address | Na, GA |
| Subwatershed | No Business Creek-Yellow River (HUC 030701030401) |
| NAICS | 236115 – New Single-Family Housing Construction [except For-Sale Builders] |
| SIC | 1521 – Single-Family Housing Construction |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES GAR367622.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES GAR367622.
Inspections
EPA’s inspection file holds no inspection for NPDES GAR367622.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES GAR367622.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, GAR367622.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Na
- Every permit record in Na, A to Z
- Discharge permits in Georgia
- Every permit record in Georgia, A to Z
Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.