CEDAR RIDGE SUBDIVISION, held by Cedar Ridge Development, LLC, holds NPDES permit ILR10ZE1V. EPA’s file records it issued May 29, 2024 and expiring August 31, 2028.
CEDAR RIDGE SUBDIVISION, Edwardsville, Illinois: Coverage under a general permit ILR10ZE1V, held by Cedar Ridge Development, LLC; Construction stormwater; Effective; issued May 29, 2024, term to August 31, 2028, by IEPA.
- March 27, 2026: Follow-Up (S).
- March 12, 2026: Follow-Up (S).
Illinois holds 5,215 Construction stormwater coverages of this permit type in EPA’s file; 1,647 were issued before ILR10ZE1V.
Coverages issued nearest ILR10ZE1V
- May 25, 2024: FORD OF HOMEWOOD, Homewood, ILR10ZE5Q, held by Ford of Homewood
- May 25, 2024: CREEKSIDE PARK, Willowbrook, ILR10ZE5S, held by Village of Willowbrook
- May 26, 2024: NEW DRIVEWAY CONNECTION AT PETERSON ROAD, Mundelein, ILR10ZE5T, held by B & B Permanent Seeding
- May 26, 2024: MCHENRY ALL SAFE SELF-STORAGE, SITE EXPANSION, Mchenry, ILR10ZE5U, held by All Safe Self-Storage
- May 26, 2024: BRENTWOOD ELEMENTARY SCHOOL IMPROVEMENTS, Des Plaines, ILR10ZE60, held by Illinois
- May 29, 2024: PARKER GLEN II APARTMENTS AND SUBDIVISION, Champaign, ILR10ZE5N, held by Woda Cooper
- May 29, 2024: ESP PONTIAC, Pontiac, ILR10ZE65, held by TBD
- May 29, 2024: ESP BOURBONNAIS, Bourbonnais, ILR10ZE66, held by TBD
- May 29, 2024: PIONEER PKWY AND UNIVERSITY ST. INTERSECTION RECONSTRUCTION, Peoria, ILR10ZE67, held by Gensini Excavating, Inc.
- May 29, 2024: NEW CAR WASH - YORKVILLE, Yorkville, ILR10ZE68, held by Car Wash Pro Designers
CEDAR RIDGE SUBDIVISION among its neighbors
EPA’s permit file holds 12 discharge permits in the Mooney Creek subwatershed (HUC 071401010205), ILR10ZE1V among them.
Other permits in the Mooney Creek subwatershed (HUC 071401010205)
- BLACKBURN ROAD STORAGE UNIT SITE, Edwardsville: ILR10ZEEE, minor permit, permit term to August 31, 2028
- EDWARDSVILLE FIRE DEPT. EAST SUBSTATION, Edwardsville: ILR10ZC05, minor permit, permit term to August 31, 2028
- HAWTHORNE HILLS SUBDIVISION PHASE 4, Edwardvsille: ILR10ZG1V, minor permit, permit term to August 31, 2028
- HOLYOAKE ROAD IMPROVEMENTS, Edwardsville: ILR10ZH0B, minor permit, permit term to August 31, 2028
- PANDA EXPRESS GLEN CARBON, Village Of Glen Carbon: ILR10ZEKC, minor permit, permit term to August 31, 2028
- PARK NORTH DEVELOPMENT, Edwardsville: ILR10ZCNJ, minor permit, permit term to August 31, 2028
- PFUND INDUSTRIAL PARK, Edwardsville: ILR10ZDY6, minor permit, permit term to August 31, 2028
- PLUMMER FAMILY PARK, Edwardsville: ILR10ZDV7, minor permit, permit term to August 31, 2028
- RICHARDS BRICK COMPANY, Edwardsville: ILR001832, minor permit, permit term to June 1, 2008
- SAVANNAH CROSSING PHASE 6, Glen Carbon: ILR10ZDHE, minor permit, permit term to August 31, 2028
Identity
| Facility as filed | CEDAR RIDGE SUBDIVISION |
|---|---|
| Permittee as filed | Cedar Ridge Development, LLC |
| NPDES ID | ILR10ZE1V |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | May 29, 2024 |
| Expiration date | August 31, 2028 |
| Issuing agency | IEPA |
| Address | Edwardsville, IL 62025 |
| Subwatershed | Mooney Creek (HUC 071401010205) |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES ILR10ZE1V.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES ILR10ZE1V.
Inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| March 27, 2026 | Follow-Up | S |
| March 12, 2026 | Follow-Up | S |
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES ILR10ZE1V.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, ILR10ZE1V.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Edwardsville
- Every permit record in Edwardsville, A to Z
- Discharge permits in Illinois
- Every permit record in Illinois, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.