Clean Water Act discharge permit · NPDES MAR1002G9

REYNOLDS AVENUE SUBSTATION PROJECT, Rehoboth, MA: NPDES MAR1002G9 discharge permit, effluent exceedances, inspections, penalties

REYNOLDS AVENUE SUBSTATION PROJECT, held by Massachusetts Electric Company and New England Power Company, holds NPDES permit MAR1002G9. EPA’s file records it issued January 23, 2020 and expiring February 15, 2022.

REYNOLDS AVENUE SUBSTATION PROJECT, Rehoboth, Massachusetts: Coverage under a general permit MAR1002G9, held by Massachusetts Electric Company and New England Power Company; Construction stormwater; Administratively continued (past its expiration date and still in force until reissued); issued January 23, 2020, term to February 15, 2022, by U.S. EPA.

Massachusetts holds 3,320 Construction stormwater coverages of this permit type in EPA’s file; 150 were issued before MAR1002G9.

Coverages issued nearest MAR1002G9

REYNOLDS AVENUE SUBSTATION PROJECT among its neighbors

EPA’s permit file holds 59 discharge permits in the Taunton River-Frontal Mount Hope Bay subwatershed (HUC 010900040804), MAR1002G9 among them.

Other permits in the Taunton River-Frontal Mount Hope Bay subwatershed (HUC 010900040804)

What the register holds for REYNOLDS AVENUE SUBSTATION PROJECT: its NPDES ID, its permit type and status, its dates, its address in Rehoboth, Massachusetts. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES MAR1002G9.

Identity

Facility as filedREYNOLDS AVENUE SUBSTATION PROJECT
Permittee as filedMassachusetts Electric Company and New England Power Company
NPDES IDMAR1002G9
Permit statusAdministratively continued (past its expiration date and still in force until reissued)
Permit typeCoverage under a general permit
Discharger classMinor discharger
Facility typeNot a publicly owned treatment works
ProgramConstruction stormwater
IssuedJanuary 23, 2020
Expiration dateFebruary 15, 2022
Issuing agencyU.S. EPA
AddressRehoboth, MA 02769
SubwatershedTaunton River-Frontal Mount Hope Bay (HUC 010900040804)

Effluent limits and exceedances

EPA’s limits and effluent violation files hold no pollutant row for NPDES MAR1002G9.

Inspections, violations and enforcement

EPA’s single-event violation file, as loaded, holds no violation for NPDES MAR1002G9.

Inspections

EPA’s inspection file holds no inspection for NPDES MAR1002G9.

Formal enforcement and penalties

0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.

Informal enforcement

EPA’s informal enforcement file holds no action for NPDES MAR1002G9.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, MAR1002G9.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.

What this page shows

This public-records page covers NPDES permit MAR1002G9, held by Massachusetts Electric Company and New England Power Company for the REYNOLDS AVENUE SUBSTATION PROJECT in Rehoboth, Massachusetts, with a status of administratively continued and a minor discharger class. The register lists 0 pollutants under a numeric limit and 0 pollutants with an effluent exceedance, and it records no effluent or single-event violation for this permit.