Clean Water Act discharge permit · NPDES MAR1004KI
NAGOG POND INTAKE REPLACEMENT PHASE II, Acton, MA: NPDES MAR1004KI discharge permit, effluent exceedances, inspections, penalties
- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
NAGOG POND INTAKE REPLACEMENT PHASE II, held by D&C Construction Co., Inc., holds NPDES permit MAR1004KI. EPA’s file records it issued April 6, 2023 and expiring February 16, 2027.
NAGOG POND INTAKE REPLACEMENT PHASE II, Acton, Massachusetts: Coverage under a general permit MAR1004KI, held by D&C Construction Co., Inc.; Construction stormwater; Effective; issued April 6, 2023, term to February 16, 2027, by U.S. EPA.
Massachusetts holds 3,320 Construction stormwater coverages of this permit type in EPA’s file; 1,232 were issued before MAR1004KI.
Coverages issued nearest MAR1004KI
- April 5, 2023: SCRANTON MAIN, LLC, Falmouth, MAR1004KB, held by NEI GC, Inc.
- April 6, 2023: 698 MAIN STREET, STURBRIDGE, MA, Sturbridge, MAR1004KE, held by A. Crane Construction, LLC.
- April 6, 2023: REPLACEMENT OF WATER MAINS BOSTON WATER AND SEWER COMMISSION 19-308-001, Boston, MAR1004KF, held by P. Gioioso & Sons Inc / Mario Romania
- April 6, 2023: WINTHROP PARK IMPROVEMENTS PROJECT, Boston, MAR1004KG, held by Sciaba Construction Corp.
- April 6, 2023: NEW INPATIENT BUILDING, Worcester, MAR1004KH, held by Whiting-Turner
- April 8, 2023: WASHINGTON STATION, Canton, MAR1004KJ, held by Washington Station, LLC
- April 10, 2023: 586 MANLEY STREET WAREHOUSE DEVELOPMENT, West Bridgewater, MAR1004KK, held by Cranshaw Construction
- April 11, 2023: THE ESTATES AT STEPLAR CROSSING, Easthampton, MAR1004KM, held by G&G Construction Company, Inc.
- April 11, 2023: RANDOLF - BRIDGE REPLACEMENT RTE 24 OVER CANTON STREET, Randolf, MAR1004KN, held by Massachusetts Department of Transportation
- April 11, 2023: ZPTII-270 FERENZ, Belchertown, MAR1004KP, held by ZPD-PT Solar Project 2017-040 LLC
NAGOG POND INTAKE REPLACEMENT PHASE II among its neighbors
EPA’s permit file holds 37 discharge permits in the Fort Pond Brook subwatershed (HUC 010700050203), MAR1004KI among them.
Other permits in the Fort Pond Brook subwatershed (HUC 010700050203)
- #608229, ACTON, INTERSECTION IMPROVEMENTS & RELATED WORK AT KELLY'S CORNER, Acton: MAR1004BV, minor permit, permit term to February 16, 2027
- 1-5 NAGOG PARK, Acton: MAR10051H, minor permit, permit term to February 16, 2027
- 123 QUARRY ROAD, Acton: MAR1005WX, minor permit, permit term to February 16, 2027
- 1440-1450 MAIN STREET, Concord: MAR1005R3, minor permit, permit term to February 16, 2027
- 208 LITTLETON ROAD IN WESTFORD, MA, Westford: MAR10057J, minor permit, permit term to February 16, 2027
- 59-63 HILDRETH STREET, Westford: MAR10043W, minor permit, permit term to February 16, 2027
- ACTON TOWN OF MS4, Acton: MAR041238, not classed
- ACTON WATER SOLAR PROJECT - LAWSBROOK ROAD, Acton: MAR1003EI, minor permit, permit term to February 15, 2022
- BAXTER MEDICAL MANUFACTURING, Acton: MANOEJ0AI, minor permit, permit term to September 15, 2027
- BOXBOROUGH TOWN OF, Boxborough: MAR041183, not classed
What the register holds for NAGOG POND INTAKE REPLACEMENT PHASE II: its NPDES ID, its permit type and status, its dates, its address in Acton, Massachusetts. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES MAR1004KI.
Identity
| Facility as filed | NAGOG POND INTAKE REPLACEMENT PHASE II |
|---|---|
| Permittee as filed | D&C Construction Co., Inc. |
| NPDES ID | MAR1004KI |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | April 6, 2023 |
| Expiration date | February 16, 2027 |
| Issuing agency | U.S. EPA |
| Address | Acton, MA 01720 |
| Subwatershed | Fort Pond Brook (HUC 010700050203) |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES MAR1004KI.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES MAR1004KI.
Inspections
EPA’s inspection file holds no inspection for NPDES MAR1004KI.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES MAR1004KI.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, MAR1004KI.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Acton
- Every permit record in Acton, A to Z
- Discharge permits in Massachusetts
- Every permit record in Massachusetts, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.