Clean Water Act discharge permit · NPDES NCC242928

SPRING HOPE 115KV SUBSTATION REBUILD, Spring Hope, NC: NPDES NCC242928 discharge permit, effluent exceedances, inspections, penalties

SPRING HOPE 115KV SUBSTATION REBUILD, held by Duke Energy Progress, LLC., holds NPDES permit NCC242928. EPA’s file records it issued September 24, 2024 and expiring March 31, 2029. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

What the register holds for SPRING HOPE 115KV SUBSTATION REBUILD: its NPDES ID, its permit type and status, its dates, its address in Spring Hope, North Carolina. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES NCC242928.

Identity

Facility as filedSPRING HOPE 115KV SUBSTATION REBUILD
Permittee as filedDuke Energy Progress, LLC.
NPDES IDNCC242928
Permit statusEffective
Permit typeCoverage under a general permit
Discharger classMinor discharger
Facility typeNot a publicly owned treatment works
IssuedSeptember 24, 2024
Expiration dateMarch 31, 2029
AddressSpring Hope, NC 27882
SubwatershedUpper Sapony Creek (HUC 030201010604)

Cited to the EPA ICIS-NPDES permit file (ECHO download).

Effluent limits and exceedances

EPA’s limits and effluent violation files hold no pollutant row for NPDES NCC242928.

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

EPA’s single-event violation file, as loaded, holds no violation for NPDES NCC242928.

Velarion’s copy of EPA’s ICIS-NPDES files does not include the inspections, formal enforcement actions and informal enforcement actions files, so this page shows none of them. EPA’s free Detailed Facility Report on ECHO lists this permit’s inspections, enforcement actions and penalties.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, NCC242928.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID NCC242928 there.

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.

What this page shows

The Spring Hope 115KV Substation Rebuild general permit coverage (NPDES ID NCC242928), held by Duke Energy Progress, LLC in Spring Hope, North Carolina, is one of 18 general permit coverages on EPA's NPDES register in that city, and it is one of 10 NPDES permits in the Upper Sapony Creek subwatershed. Of the 18 Spring Hope coverages, 33.3% were issued before this one, and none of the 18 has a recorded violation.