Clean Water Act discharge permit · NPDES SC0045462

CITY OF FLORENCE PEE DEE RIVER - WATER RECLAMATION FACILITY, Florence, SC: NPDES SC0045462 discharge permit, effluent exceedances, inspections, penalties

CITY OF FLORENCE PEE DEE RIVER - WATER RECLAMATION FACILITY, held by FLORENCE CITY OF, holds NPDES permit SC0045462. EPA’s file records it issued October 22, 2019 and expiring April 30, 2023. The status and dates are as EPA’s permit file stood when Velarion loaded it (October 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

Identity

Facility as filedCITY OF FLORENCE PEE DEE RIVER - WATER RECLAMATION FACILITY
Permittee as filedFLORENCE CITY OF
NPDES IDSC0045462
Permit statusAdministratively continued (past its expiration date and still in force until reissued)
Permit typeIndividual permit
Discharger classMajor discharger
Facility typePublicly owned treatment works
ProgramPublicly owned treatment works
IssuedOctober 22, 2019
Expiration dateApril 30, 2023
Issuing agencyState
AddressFlorence, SC 29501
SubwatershedBachelor Creek-Great Pee Dee River (HUC 030402011003)
Program components on filePOTW, Pretreatment
NAICS221320 – Sewage Treatment Facilities
SIC4952 – Sewerage Systems
Other EPA IDs (FRS)ICIS-AIR source SC00010400079

Cited to the EPA ICIS-NPDES permit file (ECHO download) and EPA’s NAICS/SIC and component files, the same download; cross-program IDs from EPA’s FRS facility-registry crosswalk.

Effluent limits and exceedances

An effluent exceedance is a discharge monitoring report value over the permit’s numeric limit (EPA’s violation code E90). A violation of any kind also counts a report not filed. Each row is EPA’s own count for that pollutant.

Pollutant or measureLimitsViolations, any kindEffluent exceedancesLatest exceedanceLargest exceedance, as filed
Solids, total suspended499May 31, 2025363% over the limit
BOD, 5-day, 20 deg. C488March 31, 202599,999% over the limit
E. coli466May 31, 202599,999% over the limit
Flow, in conduit or thru treatment plant244February 28, 201011% over the limit
Coliform, fecal general022January 31, 201899,999% over the limit
Oxygen demand, ultimate211April 30, 202317% over the limit
pH211November 30, 2018
Nitrogen, total [as N]4200
Phosphorus, total [as P]4200
Solids, suspended percent removal140
%Effect Static Renewal 7 Day Chronic Ceriodaphnia dubia220
BOD, 5-day, percent removal120
Nitrogen, ammonia total [as N]400
Chlorine, total residual400
Mercury, total [as Hg]400
Oxygen, dissolved [DO]100

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

DateWhat EPA recordedAgency
September 29, 2025Permit Violations - Violation Specified in CommentST6
September 10, 2025WW SSO - Failure to report violation that may endanger public health 122.41(l)(7)ST6
September 10, 2025Permit Violations - Violation Specified in CommentST6
June 4, 2025Permit Violations - Violation Specified in CommentST6
February 17, 2023Pretreatment - Failure to Conduct InspectionsST6
April 12, 2022Monitoring Violations - Invalid/Unrepresentative SampleST6
August 4, 2021Pretreatment - Failure to submit required report (non-DMR)ST6
August 1, 2021Pretreatment - Failure to submit required report (non-DMR)ST6
October 26, 2020Management Practice Violations - Failure to Maintain RecordsST6
October 26, 2020Monitoring Violations - Improper Analysis or Lab ErrorST6
October 26, 2020Permit Violations - Violation Specified in CommentST6

Velarion’s copy of EPA’s ICIS-NPDES files does not include the inspections, formal enforcement actions and informal enforcement actions files, so this page shows none of them. EPA’s free Detailed Facility Report on ECHO lists this permit’s inspections, enforcement actions and penalties.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, SC0045462.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID SC0045462 there.

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.