Clean Water Act discharge permit · NPDES TXR1510WC
EGYPT DISTRIBUTION PROJECT, Conroe, TX: NPDES TXR1510WC discharge permit, effluent exceedances, inspections, penalties
- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
EGYPT DISTRIBUTION PROJECT, held by Entergy Texas, Inc., holds NPDES permit TXR1510WC, which discharges to West Fork White Oak Creek. EPA’s file records it issued October 9, 2025 and expiring March 4, 2028.
EGYPT DISTRIBUTION PROJECT, Conroe, Texas: Coverage under a general permit TXR1510WC, held by Entergy Texas, Inc.; Construction stormwater; Effective; issued October 9, 2025, term to March 4, 2028; discharges to WEST FORK WHITE OAK CREEK.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 16,322 were issued before TXR1510WC. Entergy Texas, Inc. holds 12 permits in Texas.
Other permits held by Entergy Texas, Inc.
- ENTERGY LEGEND SUBSTATION, Port Arthur: TXR1503ZA, issued July 31, 2026
- DENBURY DEVELOPMENT EAST & WEST LINES UPGRADE, Conroe: TXR1505OM, issued September 25, 2023
- WHITE WATER DISTRIBUTION, Batson: TXR1534UI, issued April 21, 2025
- CERTAINTEED BRYAN TEXAS 69KV LINE RELOCATION PROJECT, Bryan: TXR1548WD, issued October 16, 2025
- DEER-DOUCETTE TRANSMISSION LINE REBUILD, Woodville: TXR1555UJ, issued April 24, 2025
- ENTERGY - SH21 SEGMENT 2, Madisonville: TXR1555YE, issued May 7, 2026
- MILLBEND DISTRIBUTION PROJECT, Porter: TXR1563QT, issued May 3, 2024
- PINEY WOODS SOLAR, Huntsville: TXR1570WM, issued November 18, 2025
- FAULKNER RIDGE DEVELOPMENT UTILITY INSTALATION, Cleveland: TXR1572XB, issued January 22, 2026
- SLEEPY HOLLOW- DISTRIBUTION REBUILD AND UPGRADE, The Woodlands: TXR1576OL, issued September 25, 2023
Coverages issued nearest TXR1510WC
- October 9, 2025: MAPLE WOODS, Hockley, TXR1504WC, held by D.R. Horton - Texas, Ltd.
- October 9, 2025: CELINA FIRE STATION 4 - COMMERCIAL, Celina, TXR1505WC, held by Crossland Construction Company INC.
- October 9, 2025: LEXINGTON HEIGHTS, Willis, TXR1506WC, held by D.R. Horton - Texas, Ltd.
- October 9, 2025: KAMMERER DR EXTENSION & BRIARLEY REC CENTER, Montgomery, TXR1508WC, held by DaCo Paving, Inc.
- October 9, 2025: LINE S20 REPLACEMENT, Lancaster, TXR1509WC, held by Atmos Energy Corporation
- October 9, 2025: MERAKI, Forney, TXR1512WC, held by Highland Homes-Dallas, LLC
- October 9, 2025: TXDOT PHR CSJ 1427-02-008, Pharr, TXR1513WC, held by Texas Department of Transportation
- October 9, 2025: TEXAS DEPARTMENT OF TRANSPORTATION, Raymondville, TXR1514WC, held by Texas Department of Transportation
- October 9, 2025: SKYVIEW SUBSTATION, Euless, TXR1515WC, held by Oncor Electric Delivery Company LLC
- October 9, 2025: LT VISIONARY, Rosenberg, TXR1591WB, held by Epoch Construction
EGYPT DISTRIBUTION PROJECT among its neighbors
EPA’s permit file holds 76 discharge permits in the Town Creek-Conroe Lake subwatershed (HUC 120401010206), TXR1510WC among them. Its county holds 1,439, 16 of them major permits; TXR1510WC is a minor permit.
Other permits in the Town Creek-Conroe Lake subwatershed (HUC 120401010206)
- 10533 W FM 1097, Willis: TXR1568MO, minor permit, discharging to LAKE CONROE, permit term to March 4, 2028
- 10918 DECATUR STREET, Willis: TXR1513ZB, minor permit, discharging to LAKE CONROE, permit term to March 4, 2028
- ADF EXCAVATION PIT, Willis: TXR05DX64, minor permit, permit term to August 13, 2021
- BRIARLEY, Montgomery: TXR1579UB, minor permit, discharging to THE SAN JACINTO RIVER BASIN, permit term to March 4, 2028
- CAPE CONROE, Montgomery: TXR1556XM, minor permit, discharging to LAKE CONROE, permit term to March 4, 2028
- CHAPEL BEND, Montgomery: TXR1565ME, minor permit, discharging to CARWILE CREEK, permit term to March 4, 2028
- CHAPEL RUN, Conroe: TXR1597XN, minor permit, discharging to WEST FORK SAN JACINTO RIVER, permit term to March 4, 2028
- DEL LAGO ESTATES WWTP, Montgomery: TX0104060, minor permit, discharging to LAKE CONROE, permit term to June 1, 2022
- DEL LAGO WWTF, Montgomery: TX0089630, minor permit, discharging to LAKE CONROE, permit term to June 1, 2022
- DETENTION TO SERVE TRIB 4X-1 AT THE WOODLANDS HILL, Willis: TXR1560PF, minor permit, discharging to STEWARTS CREEK, permit term to March 4, 2028
What the register holds for EGYPT DISTRIBUTION PROJECT: its NPDES ID, its permit type and status, its dates, its address in Conroe, Texas, its receiving water. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES TXR1510WC.
Identity
| Facility as filed | EGYPT DISTRIBUTION PROJECT |
|---|---|
| Permittee as filed | Entergy Texas, Inc. |
| NPDES ID | TXR1510WC |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | October 9, 2025 |
| Expiration date | March 4, 2028 |
| Address | Conroe, TX 77304 |
| Receiving water | WEST FORK WHITE OAK CREEK |
| Subwatershed | Town Creek-Conroe Lake (HUC 120401010206) |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES TXR1510WC.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES TXR1510WC.
Inspections
EPA’s inspection file holds no inspection for NPDES TXR1510WC.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES TXR1510WC.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, TXR1510WC.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Conroe
- Every permit record in Conroe, A to Z
- Discharge permits in Texas
- Every permit record in Texas, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.