Velarion Records
Follow this permit Velarion Records emails you this permit’s record, cited to the public filing, and tells you when the register changes it. Free.
We’ll email you a link to confirm. The continuous daily watch on every change is the paid alert. Unsubscribe any time.
Also free: The Pay Desk, the weekly executive pay briefing.

Clean Water Act discharge permit · NPDES TXR1523PM

PEC YARRINGTON SUBSTATION, Kyle, TX: NPDES TXR1523PM discharge permit, effluent exceedances, inspections, penalties

PEC YARRINGTON SUBSTATION, held by Lambda Construction I, Ltd., holds NPDES permit TXR1523PM, which discharges to Lower Blanco River. EPA’s file records it issued January 8, 2024 and expiring March 4, 2028. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

What the register holds for PEC YARRINGTON SUBSTATION: its NPDES ID, its permit type and status, its dates, its address in Kyle, Texas, its receiving water. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES TXR1523PM.

Identity

Facility as filedPEC YARRINGTON SUBSTATION
Permittee as filedLambda Construction I, Ltd.
NPDES IDTXR1523PM
Permit statusEffective
Permit typeCoverage under a general permit
Discharger classMinor discharger
Facility typeNot a publicly owned treatment works
ProgramConstruction stormwater
IssuedJanuary 8, 2024
Expiration dateMarch 4, 2028
AddressKyle, TX 78640
Receiving waterLOWER BLANCO RIVER
SubwatershedBlanco River (HUC 121002030205)

Cited to the EPA ICIS-NPDES permit file (ECHO download).

Effluent limits and exceedances

EPA’s limits and effluent violation files hold no pollutant row for NPDES TXR1523PM.

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

EPA’s single-event violation file, as loaded, holds no violation for NPDES TXR1523PM.

Inspections

EPA’s inspection file holds no inspection for NPDES TXR1523PM.

Formal enforcement and penalties

0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.

Informal enforcement

EPA’s informal enforcement file holds no action for NPDES TXR1523PM.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, TXR1523PM.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID TXR1523PM there.

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.

What this page shows

PEC YARRINGTON SUBSTATION is one of 336 storm water construction permits in Hays County, and 0.6% of that group has a violation on file. The permit sits among 46 NPDES permits in the Blanco River subwatershed, and it has no pollutants under a numeric limit and no pollutants with an effluent exceedance. Of the 336 Hays County storm water construction permits, 8.3% carry an earlier issue date than this one.