Clean Water Act discharge permit · NPDES TXR1547IG
CELANESE PANTHER PIPELINE, Pasadena, TX: NPDES TXR1547IG discharge permit, effluent exceedances, inspections, penalties
- Administratively continuedPermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
CELANESE PANTHER PIPELINE, held by Dapco Services, Inc., holds NPDES permit TXR1547IG, which discharges to Taylor Bayou. EPA’s file records it issued March 1, 2022 and expiring March 4, 2023.
CELANESE PANTHER PIPELINE, Pasadena, Texas: Coverage under a general permit TXR1547IG, held by Dapco Services, Inc.; Construction stormwater; Administratively continued (past its expiration date and still in force until reissued); issued March 1, 2022, term to March 4, 2023; discharges to TAYLOR BAYOU.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 659 were issued before TXR1547IG.
Coverages issued nearest TXR1547IG
- March 1, 2022: CREEKLAND ALL PHASES OF CONSTRUCTION, Cypress, TXR1536IG, held by 5J Services, LLC
- March 1, 2022: ASSEMBLY PARK, Plano, TXR1540IG, held by Plano Mall Owner, LP
- March 1, 2022: FOUNTAIN HILLS ADDITION, Lubbock, TXR1542IG, held by Sticks & Stones Designs, LLC
- March 1, 2022: HONEYSUCKLE RANCH PHASE 2, Decatur, TXR1543IG, held by F X 5 Construction & Excavation, Inc.
- March 1, 2022: TURTLE CREEK NO 3, San Antonio, TXR1544IG, held by ARCHER WESTERN CONSTRUCTION, LLC
- March 1, 2022: DEL RIO LOFTS, Del Rio, TXR1549IG, held by Tan Construction, Inc.
- March 1, 2022: BRECKENRIDGE EAST SECTION 1, Spring, TXR1550IG, held by Durwood Greene Construction
- April 1, 2022: SEVEN HILLS ELEMENTARY SCHOOL, Newark, TXR1553IP, held by Pogue Construction Co., LP
- April 1, 2022: 24 TREATED TRANSMISSION WATERLINE PROJECT - PHASE 3, Odem, TXR1554IP, held by S. J. Louis Construction of Texas Ltd.
- April 1, 2022: PIRKEY POWER PLANT BOTTOM ASH PONDS CLOSURE, Hallsville, TXR1555IP, held by Southwestern Electric Power Company
CELANESE PANTHER PIPELINE among its neighbors
EPA’s permit file holds 560 discharge permits in the Clear Creek-Frontal Galveston Bay subwatershed (HUC 120402040100), TXR1547IG among them.
Other permits in the Clear Creek-Frontal Galveston Bay subwatershed (HUC 120402040100)
- 10 PUBLIC SANITARY SEWER RELOCATION PLANS FOR EDG, Seabrook: TXR1567OE, minor permit, discharging to TAYLOR LAKE, permit term to March 4, 2028
- 11806 PORT ROAD, Seabrook: TXR1501PX, minor permit, discharging to BAYPORT CHANNEL, permit term to March 4, 2028
- 3223-01 HMCL MOB3 - ASC, Houston: TXR1557VH, minor permit, discharging to CLEAR LAKE, permit term to March 4, 2028
- 34 ACRES EGRET BAY MASS GRADING, League City: TXR1555QU, minor permit, discharging to ROBINSON BAYOU, permit term to March 4, 2028
- 4 HORN PROPERTIES, Pasadena: TXR1565VB, minor permit, discharging to MIDDLE BAYOU, permit term to March 4, 2028
- 42 WL FROM CLCWA WP 3 TO LEAGUE CITY BOOSTER PUMP STATION, Webster: TXR1580WY, minor permit, discharging to COW BAYOU, permit term to March 4, 2028
- 541 WATER SYSTEM, Alvin: TX0141623, minor permit, discharging to DETENTION BASIN CHIGGER CRK;CLEAR CREEK, permit term to July 8, 2027
- 6951 MCHARD RD--JOJES CAPITAL, Houston: TXR1545QD, minor permit, discharging to CLEAR CREEK ABOVE TIDAL, permit term to March 4, 2028
- A SCHULMAN, La Porte: TX0111350, minor permit, discharging to UNNAMED DITCH; TAYLOR BAYOU, permit term to August 1, 2021
- ACC HOU - MCHARD, Fresno: TXR05GQ82, minor permit, permit term to August 13, 2026
What the register holds for CELANESE PANTHER PIPELINE: its NPDES ID, its permit type and status, its dates, its address in Pasadena, Texas, its receiving water. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES TXR1547IG.
Identity
| Facility as filed | CELANESE PANTHER PIPELINE |
|---|---|
| Permittee as filed | Dapco Services, Inc. |
| NPDES ID | TXR1547IG |
| Permit status | Administratively continued (past its expiration date and still in force until reissued) |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | March 1, 2022 |
| Expiration date | March 4, 2023 |
| Address | Pasadena, TX 77507 |
| Receiving water | TAYLOR BAYOU |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Clear Creek-Frontal Galveston Bay (HUC 120402040100) |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES TXR1547IG.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES TXR1547IG.
Inspections
EPA’s inspection file holds no inspection for NPDES TXR1547IG.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES TXR1547IG.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, TXR1547IG.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Pasadena
- Every permit record in Pasadena, A to Z
- Discharge permits in Texas
- Every permit record in Texas, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.