- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
AMHERST GLADSTONE PHOENIX 69KV REMOVAL, held by Appalachian Power Co, holds NPDES permit VAR10X312, which discharges to Tye River-Brown Creek. EPA’s file records it issued July 1, 2024 and expiring June 30, 2029.
AMHERST GLADSTONE PHOENIX 69KV REMOVAL, Amherst, Virginia: Coverage under a general permit VAR10X312, held by Appalachian Power Co; Construction stormwater; Effective; issued July 1, 2024, term to June 30, 2029, by VA DEQ; discharges to Tye River-Brown Creek.
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 3,403 were issued before VAR10X312. Appalachian Power Co holds 15 permits in Virginia.
Other permits held by Appalachian Power Co
- JOSHUA FALLS 765KV SUBSTATION UPGRADES, Lynchburg: VAR10R058, issued July 1, 2019
- BOXWOOD LAYDOWN YARD, Amherst: VAR10R209, issued July 1, 2019
- SOAPSTONE 138 KV SUBSTATION, Schuyler: VAR10R267, issued July 1, 2019
- RIVERVILLE 138 KV SUBSTATION EXPANSION, Gladstone: VAR10R268, issued July 1, 2019
- PATRICK HENRY 138 KV STATION, Bassett: VAR10S702, issued July 1, 2019
- BROSVILLE 138 KV LINE EXTENSION, Cascade: VAR10T079, issued July 1, 2019
- WINSTON AVENUE 69KV SUBSTATION, Roanoke: VAR10T095, issued July 1, 2019
- BROSVILLE 138 KV STATION, Cascade: VAR10T205, issued July 1, 2019
- POINT LOOKOUT 69KV STATION, Independence: VAR10V921, issued July 1, 2024
- LEVISA 69 KV STATION, Buchanan: VAR10V970, issued July 1, 2024
Coverages issued nearest VAR10X312
- July 1, 2024: PAUL VI CATHOLIC HIGH SCHOOL, Chantilly, VAR10X306, held by Diocese of Arlington
- July 1, 2024: FLINT HILL - ATLANTIC CONDOMINIUMS PARCEL A AND B, Charlottesville, VAR10X307, held by Atlantic builders LTD
- July 1, 2024: PEAKE ALLSTARS GYM, Chesapeake, VAR10X308, held by CL Pincus Jr. & Co.
- July 1, 2024: HAMPSTEAD SUBDIVISION: SECTION FOUR, Stafford, VAR10X309, held by Hampstead Development Inc.
- July 1, 2024: LAWS FORD MITIGATION BANK, Catlett, VAR10X310, held by HGS, LLC
- July 1, 2024: SHERANDO PARK SOCCER FIELD AND SOFTBALL FIELD INST, Stephens City, VAR10X313, held by Frederick County Parks and Recreation
- July 1, 2024: ARBOR ROW BLOCK C-2, Mclean, VAR10X315, held by ARBOR ROW C-2, LLC
- July 1, 2024: VILLAS AT HILLTOP, Spotsylvania, VAR10X317, held by ESC Hilltop, LLC
- July 1, 2024: SPRINGLINE PARCEL 3 - NORTHBEND, Richmond, VAR10X318, held by Collins Chesterfield II LLC
- July 1, 2024: AZALEA SPRINGS SUBDIVISION, Charlottesville, VAR10X320, held by Stanley Martin Homes, LLC
AMHERST GLADSTONE PHOENIX 69KV REMOVAL among its neighbors
EPA’s permit file holds 2 discharge permits in the Rocky Creek-Buffalo River subwatershed (HUC 020802030604), VAR10X312 among them.
Other permits in the Rocky Creek-Buffalo River subwatershed (HUC 020802030604)
- AMHERST COUNTY LANDFILL PERMIT NUMBER 181, Amherst: VA0088684, minor permit, discharging to Buffalo River-Rocky Creek, permit term to December 31, 2024
What the register holds for AMHERST GLADSTONE PHOENIX 69KV REMOVAL: its NPDES ID, its permit type and status, its dates, its address in Amherst, Virginia, its receiving water. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES VAR10X312.
Identity
| Facility as filed | AMHERST GLADSTONE PHOENIX 69KV REMOVAL |
|---|---|
| Permittee as filed | Appalachian Power Co |
| NPDES ID | VAR10X312 |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | July 1, 2024 |
| Expiration date | June 30, 2029 |
| Issuing agency | VA DEQ |
| Address | Amherst, VA 24580 |
| Receiving water | Tye River-Brown Creek |
| Subwatershed | Rocky Creek-Buffalo River (HUC 020802030604) |
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES VAR10X312.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES VAR10X312.
Inspections
EPA’s inspection file holds no inspection for NPDES VAR10X312.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES VAR10X312.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, VAR10X312.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
Nearby on the register
- Discharge permits in Amherst
- Every permit record in Amherst, A to Z
- Discharge permits in Virginia
- Every permit record in Virginia, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.