EPA · discharge permits by watershed

Watershed 1207020503

A watershed is a unit of the national Watershed Boundary Dataset, and water crosses state lines: this one carries permits in Texas. Each permit is placed by the outfall EPA names as its representative discharge point.

This watershed contains 3 subwatersheds, each with its own page of permits. The table below is a sample of the 137 current permits recorded here

By state

Subwatersheds inside this watershed

Other watersheds

Permits discharging here

Permit holderNPDES IDCityStateProgramDischargerReceiving waterStatus and term
NORTHLANDS WWTPTX0132233GEORGETOWNTXPublicly owned treatment worksMajorJENNINGS BRANCH;COWAN CRK;BERRY CRK;SAN GABRIELAdministratively continued, 2019-04-01 to 2024-03-31
PECAN BRANCH WWTPTX0114006GEORGETOWNTXPublicly owned treatment worksMajorBRAZOS RIVER BASINAdministratively continued, 2014-05-30 to 2018-12-01
AUSTIN BLOCK & QUARRYTXR05FD48JARRELLTXIndustrial stormwaterMinorDry Berry CreekAdministratively continued, 2021-11-02 to 2026-08-13
BAER MANUFACTURINGTXRNECR52GEORGETOWNTXIndustrial stormwaterMinorDry Berry CreekAdministratively continued, 2026-07-07 to 2026-08-13
BERRY CREEKTXR1546WKGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2025-11-10 to 2028-03-04
BERRY CREEK 8B & 9TXR1524YXGEORGETOWNTXConstruction stormwaterMinor1248A BERRY CREEKEffective, 2026-07-21 to 2028-03-04
BERRY CREEK 8B & 9TXR1525YXGEORGETOWNTXConstruction stormwaterMinor1248A BERRY CREEKEffective, 2026-07-21 to 2028-03-04
BERRY CREEK AMENITY CENTERTXR1518NRGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2023-07-20 to 2028-03-04
BERRY CREEK APARTMENTS PHASE 1TXR1553WMGEORGETOWNTXConstruction stormwaterMinorSAN GABRIEL/NORTH FORK SAN GABRIEL RIVEREffective, 2025-11-17 to 2028-03-04
BERRY CREEK CROSSING WASTEWATER IMPROVEMENTSTXR1574PFGEORGETOWNTXConstruction stormwaterMinorSAN GABRIEL/NORTH FORK SAN GABRIEL RIVEREffective, 2023-12-07 to 2028-03-04
BERRY CREEK HIGHLANDS PHASE 1B & 2BTXR1525IGGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKAdministratively continued, 2022-03-01 to 2023-03-04
BERRY CREEK HIGHLANDS PHASE 6ATXR1515PLGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2024-01-03 to 2028-03-04
BERRY CREEK HIGHLANDS PHASE 8B & 9TXR1516WZGEORGETOWNTXConstruction stormwaterMinorBERRY CREEK 1248AEffective, 2026-01-13 to 2028-03-04
BERRY CREEK HIGHLANDS PHASES 8B AND 9TXR1543WYGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2026-01-12 to 2028-03-04
BERRY CREEK WASTEWATER INTERCEPTORTXR1540PUGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2024-02-01 to 2028-03-04
BERRY CREEK WWTPTX0119172GEORGETOWNTXPublicly owned treatment worksMinorBERRY CREEK;SAN BARIEL/NORTH FORKAdministratively continued, 2017-07-18 to 2020-12-01
BROKEN OAKTXR1548NUGEORGETOWNTXConstruction stormwaterMinorCOWAN CREEKEffective, 2023-07-31 to 2028-03-04
CALIBRE QUARRYTXR05GY25GEORGETOWNTXIndustrial stormwaterMinorDry Berry CreekAdministratively continued, 2026-02-10 to 2026-08-13
CELLINKTXR05GI08GEORGETOWNTXIndustrial stormwaterMinorLower Berry CreekAdministratively continued, 2024-01-11 to 2026-08-13
CENTRAL TEXAS AVIONICSTXRNECH38GEORGETOWNTXIndustrial stormwaterMinorLower Berry CreekAdministratively continued, 2024-04-03 to 2026-08-13
CHALK RIDGE SHOPTXR1518PQFLORENCETXConstruction stormwaterMinorBERRY CREEKEffective, 2024-01-22 to 2028-03-04
CHALK RIDGE SHOPTXR05GT47GEORGETOWNTXIndustrial stormwaterMinorLower Berry CreekAdministratively continued, 2025-07-16 to 2026-08-13
CHAMPION STONE QUARRYTXR05GP12GEORGETOWNTXIndustrial stormwaterMinorLower Berry CreekAdministratively continued, 2024-12-17 to 2026-08-13
CHASE BANK PARMER RANCHTXR1584VFGEORGETOWNTXConstruction stormwaterMinorCOWAN CREEKEffective, 2025-07-16 to 2028-03-04
CR 146 NEW TRUCK PARKING FACILITYTXR1580WLJARRELLTXConstruction stormwaterMinorBERRY CREEKEffective, 2025-11-13 to 2028-03-04
CR152 RV PARKTXR1529RAGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2024-05-30 to 2028-03-04
CROSS POINT PHASE 2TXR1536TCGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2024-12-23 to 2028-03-04
CSJ 0914-05-214 RONALD REAGAN BLVD AT CR 234 AND FM 1209TXR1518RPGEORGETOWNTXConstruction stormwaterMinorCOLORADO RIVEREffective, 2024-07-26 to 2028-03-04
DNT CONSTRUCTION OFFICE - GEORGETOWNTXR1543VKGEORGETOWNTXConstruction stormwaterMinorDRY BERRY CREEKEffective, 2025-08-01 to 2028-03-04
DRY BERRY CREEK INTERCEPTORTXR1583VOGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2025-08-19 to 2028-03-04
ESPINOZA STONE PIT 2TXR05GK40GEORGETOWNTXIndustrial stormwaterMinorDry Berry CreekAdministratively continued, 2024-05-03 to 2026-08-13
FEATHERGRASSTXR1585SKGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2024-10-14 to 2028-03-04
FEATHERGRASS DANIELLES TRACETXR1557SQGEORGETOWNTXConstruction stormwaterMinorBERRY CREEKEffective, 2024-11-05 to 2028-03-04
FLORENCE CBPTXG113038FLORENCETXMinorDry Berry CreekEffective, 2022-02-08 to 2026-11-06
FLORENCE QUARRYTXR05FV62GEORGETOWNTXIndustrial stormwaterMinorDry Berry CreekAdministratively continued, 2022-10-04 to 2026-08-13
FLORENCE SUBSTATIONTXR1520QWFLORENCETXConstruction stormwaterMinorBERRY CREEKEffective, 2024-05-14 to 2028-03-04
FM 972 RETAIL CENTERTXR1524VSGEORGETOWNTXConstruction stormwaterMinorUNNAMED TRIBUTARYEffective, 2025-09-02 to 2028-03-04
GEORGETOWN CBPTXG113822GEORGETOWNTXMinorDry Berry CreekEffective, 2025-02-17 to 2026-11-06
GEORGETOWN CRUSHERTXR05GL26GEORGETOWNTXIndustrial stormwaterMinorDry Berry CreekAdministratively continued, 2024-06-11 to 2026-08-13
GEORGETOWN FAMILY YMCATXR1579YMGEORGETOWNTXConstruction stormwaterMinorCOWAN CREEKEffective, 2026-06-09 to 2028-03-04

What this page shows

This page lists Clean Water Act discharge permits (EPA NPDES register) in watershed 1207020503. The page shows 137 permits, and the whole watershed in TX has 137 permits.